Possession date of SHREYA PRIDE: 30 October 2026, moved from 28 February 2023 (40 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52300030328. Status: Lapsed (registration period ended). Its completion date has moved from February 2023 to October 2026: 40 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about SHREYA PRIDE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREYA PRIDE has moved

  1. 28 February 2023

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT52300018235)

    Reason the builder gave MahaRERA: “Applied for the change in plan, which involves increase in number of apartments and floors, for that purpose required to extend the date of completion of project.”
  3. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHREYA PRIDE’s extension records on MahaRERA (P52300030328), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREYA PRIDE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52300030328
Status
Lapsed (registration period ended)
Builder
NITINKUMAR LIMBRAJ CHATEKAR
Location
Balepeer Bid, Beed · 431122
Project type
Others
Registered on
15 Aug 2021
Completion date at registration
February 2023
Latest completion date
October 2026
Delay so far
40 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHREYA PRIDE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREYA PRIDE100%3%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREYA PRIDE every month.

SHREYA PRIDE: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREYA PRIDE (7 floors)
  • Land: 275 sq m (about 0.1 acres)
  • Boundaries filed include: APPLICANTS OPEN PLOT FOR GARDEN

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREYA PRIDE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREYA PRIDE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREYA PRIDE

What is the possession date of SHREYA PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREYA PRIDE in Balepeer Bid, Beed is 30 October 2026 — 40 months later than 28 February 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHREYA PRIDE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREYA PRIDE's builder has filed on MahaRERA, the official one, is 30 October 2026, already 40 months later than the 28 February 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREYA PRIDE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Applied for the change in plan, which involves increase in number of apartments and floors, for that purpose required to extend the date of completion of project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHREYA PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREYA PRIDE in Balepeer Bid, Beed is P52300030328.

Is SHREYA PRIDE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE is registered as P52300030328 and its status is "Lapsed (registration period ended)".

What is the construction status of SHREYA PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREYA PRIDE is 3% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SHREYA PRIDE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHREYA PRIDE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE is registered on MahaRERA as P52300030328, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 40 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREYA PRIDE's possession date changes?

The latest dates are on SHREYA PRIDE's MahaRERA page (P52300030328). GharKundli's Kundli Watch sends a free WhatsApp update on SHREYA PRIDE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREYA PRIDE have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE has one building filed: SHREYA PRIDE with 7 floors.

How big is the land of SHREYA PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE stands on 275 sq m of land (about 0.1 acres).

Where can I read reviews of SHREYA PRIDE?

Google Maps has reviews of SHREYA PRIDE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREYA PRIDE?

SHREYA PRIDE by NITINKUMAR LIMBRAJ CHATEKAR is in Balepeer Bid, Beed (pincode 431122), Maharashtra, and is registered on MahaRERA as P52300030328, per GharKundli's check of MahaRERA records. Its boundaries filed there include APPLICANTS OPEN PLOT FOR GARDEN.

How many homes are in SHREYA PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE has 20 homes in 1 tower registered on MahaRERA.

When was SHREYA PRIDE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREYA PRIDE was registered on MahaRERA on 15 August 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREYA PRIDE?

No court cases are listed for SHREYA PRIDE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHREYA PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NITINKUMAR LIMBRAJ CHATEKAR.

All projects with possession due in 2026 in Beed →

Other projects in Beed

All 14 projects in Beed (431122) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.