VENKATESHWARA GREENS
by LAHOTI PROPERTIES · Khopegaon, Latur
Possession date of VENKATESHWARA GREENS: 31 December 2028, moved from 30 June 2022 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52400001029, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VENKATESHWARA GREENS?
How the possession date of VENKATESHWARA GREENS has moved
30 June 2022
Completion date given when the project was registered
30 June 2023
Extended at the builder's request (MahaRERA application EXT52400012685)
Reason the builder gave MahaRERA:
“We would like to state that above project was duly registered with regulatory authority which expired on 30/06/2022. Sir, we would like to apply for extension of our project till 30/06/2023. Sir, our project was adversely affected due to CO…” Read the full reason
“We would like to state that above project was duly registered with regulatory authority which expired on 30/06/2022. Sir, we would like to apply for extension of our project till 30/06/2023. Sir, our project was adversely affected due to COVID-19 situation and no work was carried out during the lockdown period as workers were not available as well as construction material was also not available due to transportation issues. Due to this our project got did not go as per planned schedule and booking were also not achieved due to post COVID-19 slowdown in the market. We were also financially s…”31 December 2028
Extended at the builder's request (MahaRERA application EA18122518749)
Reason the builder gave MahaRERA:
“The delay in completion of the project is due to reasons beyond the control of the promoter. The project faced financial disturbance arising from escalation in construction material costs, increase in labour expenses, and constraints in ava…” Read the full reason
“The delay in completion of the project is due to reasons beyond the control of the promoter. The project faced financial disturbance arising from escalation in construction material costs, increase in labour expenses, and constraints in availability of timely finance, which adversely affected cash flow and progress of construction.Further, the main partner of the firm, who is responsible for overall project supervision and financial decision-making, suffered serious health issues during the project period. Due to prolonged medical treatment and recovery, effective monitoring and coordinatio…”
Source: VENKATESHWARA GREENS’s extension records on MahaRERA (P52400001029), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VENKATESHWARA GREENS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52400001029
- Status
- Registered and active
- Builder
- LAHOTI PROPERTIES
- Location
- Khopegaon, Latur · 413531
- Project type
- Others
- Registered on
- 25 Jul 2017
- Completion date at registration
- June 2022
- Latest completion date
- December 2028
- Delay so far
- 78 months
- Homes
- 246
- Sold or booked
- 59%
- Towers
- 4
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VENKATESHWARA GREENS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| UNIT 1 | 100% | 0% | 0% | 0% |
| UNIT 2 | 100% | 0% | 0% | 0% |
| UNIT 3 | 100% | 88% | 83% | 0% |
| UNIT 4 | 100% | 100% | 98% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- UNIT 1: covers 0 floors
- UNIT 2: covers 0 floors
- UNIT 3: covers 0 floors
- UNIT 4: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VENKATESHWARA GREENS every month.
VENKATESHWARA GREENS: buildings, flats and land, as filed on MahaRERA
- Buildings: UNIT 1 (8 floors, 52 units) · UNIT 2 (8 floors, 52 units) · UNIT 3 (312 floors, 142 units) · UNIT 4 (3 floors, 11 units)
- Car parking: 142 open
- Land: 45,300 sq m (about 11.2 acres) · sanctioned built-up 32,561 sq m · recreational space 4,963 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VENKATESHWARA GREENS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VENKATESHWARA GREENS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VENKATESHWARA GREENS
What is the possession date of VENKATESHWARA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VENKATESHWARA GREENS in Khopegaon, Latur is 31 December 2028 — 78 months later than 30 June 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VENKATESHWARA GREENS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VENKATESHWARA GREENS's builder has filed on MahaRERA, the official one, is 31 December 2028, already 78 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VENKATESHWARA GREENS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2023, giving the reason "We would like to state that above project was duly registered with regulatory authority which expired on 30/06/2022. Sir, we would like to apply for extension of our project till 30/06/2023. Sir, our project was adversely affected due to COVID-19 situation and no work was carried out during the lockdown period as workers were not available as well as construction material was also not available due to transportation issues. Due to this our project got did not go as per planned schedule and booking were also not achieved due to post COVID-19 slowdown in the market. We were also financially s…"; to 31 December 2028, giving the reason "The delay in completion of the project is due to reasons beyond the control of the promoter. The project faced financial disturbance arising from escalation in construction material costs, increase in labour expenses, and constraints in availability of timely finance, which adversely affected cash flow and progress of construction.Further, the main partner of the firm, who is responsible for overall project supervision and financial decision-making, suffered serious health issues during the project period. Due to prolonged medical treatment and recovery, effective monitoring and coordinatio…".
What is the RERA number of VENKATESHWARA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VENKATESHWARA GREENS in Khopegaon, Latur is P52400001029.
Is VENKATESHWARA GREENS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS is registered as P52400001029 and its status is "Registered and active".
What is the construction status of VENKATESHWARA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does VENKATESHWARA GREENS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VENKATESHWARA GREENS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS is registered on MahaRERA as P52400001029, its completion date has moved 78 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VENKATESHWARA GREENS's possession date changes?
The latest dates are on VENKATESHWARA GREENS's MahaRERA page (P52400001029). GharKundli's Kundli Watch sends a free WhatsApp update on VENKATESHWARA GREENS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VENKATESHWARA GREENS have?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS has 4 buildings filed: UNIT 1 with 8 floors and 52 units; UNIT 2 with 8 floors and 52 units; UNIT 3 with 312 floors and 142 units; UNIT 4 with 3 floors and 11 units.
How much parking does VENKATESHWARA GREENS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 142 open car parking spaces for VENKATESHWARA GREENS.
How big is the land of VENKATESHWARA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS stands on 45,300 sq m of land (about 11.2 acres), with 32,561 sq m of sanctioned built-up area and 4,963 sq m of recreational open space.
Where can I read reviews of VENKATESHWARA GREENS?
Google Maps has reviews of VENKATESHWARA GREENS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VENKATESHWARA GREENS?
VENKATESHWARA GREENS by LAHOTI PROPERTIES is in Khopegaon, Latur (pincode 413531), Maharashtra, and is registered on MahaRERA as P52400001029, per GharKundli's check of MahaRERA records.
How many homes are in VENKATESHWARA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS has 246 homes in 4 towers registered on MahaRERA, and 59% of them are sold or booked.
When was VENKATESHWARA GREENS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VENKATESHWARA GREENS was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on VENKATESHWARA GREENS?
No court cases are listed for VENKATESHWARA GREENS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VENKATESHWARA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAHOTI PROPERTIES.
Check it yourself on MahaRERA
- How to check the possession date of VENKATESHWARA GREENS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Latur →
Other projects in Latur
- ICON BHASKAR
- AAKRITI ENCLAVE
- DWARKA VIHAR
- MAULI APARTMENT
- AKSHATA GOLDEN VIEW
- Omkar Heights
- SHRI GAJANAN RESIDENCY
- NAMDEV RESIDANCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.