Shrikunj
by DATTATRAY MARUTIRAO PARSHURAM · Ausa Road, Latur 413512
What’s in the report? →Possession date of Shrikunj (MahaRERA P52400025751): 28 July 2022, moved from 31 March 2021 (16 months later), and it has already passed. It has 16 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52400025751. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52400025751, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2022) has passed.
What do you want to know about Shrikunj?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shrikunj has moved
31 March 2021
Completion date given when the project was registered
28 January 2022
Extended at the builder's request (MahaRERA application EXT52400010155)
Reason the builder gave MahaRERA: “CONSTRUCTION WAS DELAYED DUE TO CORONA AND LATE DEMAND FOR APARTMENTS”
28 July 2022
Revised completion date on MahaRERA
Source: Shrikunj’s extension records on MahaRERA (P52400025751), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shrikunj
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52400025751
- Status
- Lapsed (registration period ended)
- Builder
- DATTATRAY MARUTIRAO PARSHURAM
- Location
- Ausa Road, Latur · 413512
- Project type
- Residential / Group Housing
- Registered on
- 9 Jul 2020
- Completion date at registration
- March 2021
- Latest completion date
- July 2022
- Delay so far
- 16 months
- Homes
- 16
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shrikunj, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| shrikunj | 5% | 25% | 30% | 5% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shrikunj every 1–2 months.
Shrikunj: buildings, flats and land, as filed on MahaRERA
- Buildings: shrikunj (7 floors)
- Land: 325 sq m (about 0.1 acres) · sanctioned built-up 1 sq m
- Land, as filed: 9867
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shrikunj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shrikunj: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shrikunj
What is the possession date of Shrikunj?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shrikunj in Ausa Road, Latur is 28 July 2022 — 16 months later than 31 March 2021, the date given at registration. That date has already passed.
The date has already moved 16 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shrikunj?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shrikunj's builder has filed on MahaRERA, the official one, is 28 July 2022, already 16 months later than the 31 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shrikunj extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj's builder applied to MahaRERA to extend the completion date once: to 28 January 2022, giving the reason "CONSTRUCTION WAS DELAYED DUE TO CORONA AND LATE DEMAND FOR APARTMENTS".
What is the RERA number of Shrikunj?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shrikunj in Ausa Road, Latur is P52400025751.
Is Shrikunj registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj is registered as P52400025751 and its status is "Lapsed (registration period ended)".
What is the current construction status of Shrikunj? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on shrikunj is 25% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does Shrikunj have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shrikunj safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj is registered on MahaRERA as P52400025751, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 16 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shrikunj?
Shrikunj isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shrikunj?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shrikunj: gharkundli.com/tools/property-cost-calculator
Has Shrikunj received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 28 July 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Shrikunj?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (28 July 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Shrikunj uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shrikunj was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shrikunj's possession date changes?
The latest dates are on Shrikunj's MahaRERA page (P52400025751). GharKundli's Kundli Watch sends a free WhatsApp update on Shrikunj every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shrikunj have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj has one building filed: shrikunj with 7 floors.
How big is the land of Shrikunj?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj stands on 325 sq m of land (about 0.1 acres), with 1 sq m of sanctioned built-up area.
What are the reviews of Shrikunj?
Google Maps has reviews of Shrikunj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shrikunj?
Shrikunj by DATTATRAY MARUTIRAO PARSHURAM is in Ausa Road, Latur, pincode 413512, Maharashtra, and is registered on MahaRERA as P52400025751, per GharKundli's check of MahaRERA records. Its land is filed as 9867. GharKundli lists all 102 MahaRERA projects in Latur (413512).
How many flats are in Shrikunj?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj has 16 homes in 1 tower registered on MahaRERA.
When was Shrikunj registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shrikunj was registered on MahaRERA on 9 July 2020. GharKundli did not find a title report on the land on file there.
Does Shrikunj have any legal issues or court cases?
No court cases are listed for Shrikunj on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Shrikunj?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DATTATRAY MARUTIRAO PARSHURAM.
Check it yourself on MahaRERA
- How to check the possession date of Shrikunj
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Latur (413512)
All 102 projects in Latur (413512) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.