TULSIBAAG
by SUSHMA SHAILESH KULKARNI · Tulsibaag, Latur
Possession date of TULSIBAAG: 30 April 2028, moved from 1 November 2024 (37 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52400053613, and currently active. Its completion date has moved from November 2024 to April 2028: 37 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about TULSIBAAG?
How the possession date of TULSIBAAG has moved
1 November 2024
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT52400027654)
Reason the builder gave MahaRERA: “Application for extension with 0 booking.”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: TULSIBAAG’s extension records on MahaRERA (P52400053613), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on TULSIBAAG
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52400053613
- Status
- Registered and active
- Builder
- SUSHMA SHAILESH KULKARNI
- Location
- Tulsibaag, Latur · 413531
- Project type
- Residential / Group Housing
- Registered on
- 10 Nov 2023
- Completion date at registration
- November 2024
- Latest completion date
- April 2028
- Delay so far
- 37 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 54
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of TULSIBAAG, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TULSIBAAG | 100% | 60% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULSIBAAG every month.
TULSIBAAG: buildings, flats and land, as filed on MahaRERA
- Buildings: TULSIBAAG (1 floors)
- Land: 5,415 sq m (about 1.3 acres) · sanctioned built-up 6,361 sq m · recreational space 1,410 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of TULSIBAAG →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TULSIBAAG: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TULSIBAAG
What is the possession date of TULSIBAAG?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TULSIBAAG in Tulsibaag, Latur is 30 April 2028 — 37 months later than 1 November 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for TULSIBAAG?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TULSIBAAG's builder has filed on MahaRERA, the official one, is 30 April 2028, already 37 months later than the 1 November 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of TULSIBAAG extended?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Application for extension with 0 booking.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of TULSIBAAG?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TULSIBAAG in Tulsibaag, Latur is P52400053613.
Is TULSIBAAG registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG is registered as P52400053613 and its status is "Registered and active".
What is the construction status of TULSIBAAG?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TULSIBAAG is 60% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does TULSIBAAG have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is TULSIBAAG safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG is registered on MahaRERA as P52400053613, its completion date has moved 37 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TULSIBAAG's possession date changes?
The latest dates are on TULSIBAAG's MahaRERA page (P52400053613). GharKundli's Kundli Watch sends a free WhatsApp update on TULSIBAAG every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TULSIBAAG have?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG has one building filed: TULSIBAAG with 1 floors.
How big is the land of TULSIBAAG?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG stands on 5,415 sq m of land (about 1.3 acres), with 6,361 sq m of sanctioned built-up area and 1,410 sq m of recreational open space.
Where can I read reviews of TULSIBAAG?
Google Maps has reviews of TULSIBAAG written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TULSIBAAG?
TULSIBAAG by SUSHMA SHAILESH KULKARNI is in Tulsibaag, Latur (pincode 413531), Maharashtra, and is registered on MahaRERA as P52400053613, per GharKundli's check of MahaRERA records.
How many homes are in TULSIBAAG?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG has 54 homes in 1 tower registered on MahaRERA.
When was TULSIBAAG registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSIBAAG was registered on MahaRERA on 10 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on TULSIBAAG?
No court cases are listed for TULSIBAAG on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of TULSIBAAG?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUSHMA SHAILESH KULKARNI.
Check it yourself on MahaRERA
- How to check the possession date of TULSIBAAG
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Latur →
Other projects in Latur
- ICON BHASKAR
- AAKRITI ENCLAVE
- DWARKA VIHAR
- MAULI APARTMENT
- AKSHATA GOLDEN VIEW
- Omkar Heights
- SHRI GAJANAN RESIDENCY
- Happy Planet
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.