Golden Woods Phase 2
by Santosh Kumar Hatte · Degloor Road, LaturAlso near Wadhona
Possession date of Golden Woods Phase 2: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52400051653, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Golden Woods Phase 2?
How the possession date of Golden Woods Phase 2 has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Golden Woods Phase 2’s extension records on MahaRERA (P52400051653), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Golden Woods Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52400051653
- Status
- Registered and active
- Builder
- Santosh Kumar Hatte
- Location
- Degloor Road, Latur · 413517
- Project type
- Residential / Group Housing
- Registered on
- 27 Jun 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 40
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Golden Woods Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 90% | 40% | 50% |
| B | 100% | 100% | 60% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Golden Woods Phase 2 every month.
Golden Woods Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: A (7 floors) · B (7 floors)
- Land: 1,496 sq m (about 0.4 acres) · sanctioned built-up 3,367 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Golden Woods Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Golden Woods Phase 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Golden Woods Phase 2
What is the possession date of Golden Woods Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Golden Woods Phase 2 in Degloor Road, Latur is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Golden Woods Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Golden Woods Phase 2's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Golden Woods Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Golden Woods Phase 2 in Degloor Road, Latur is P52400051653.
Is Golden Woods Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Golden Woods Phase 2 is registered as P52400051653 and its status is "Registered and active".
What is the construction status of Golden Woods Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Golden Woods Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 90% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Golden Woods Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Golden Woods Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Golden Woods Phase 2 is registered on MahaRERA as P52400051653, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Golden Woods Phase 2's possession date changes?
The latest dates are on Golden Woods Phase 2's MahaRERA page (P52400051653). GharKundli's Kundli Watch sends a free WhatsApp update on Golden Woods Phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Golden Woods Phase 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Golden Woods Phase 2 has 2 buildings filed: A with 7 floors; B with 7 floors.
How big is the land of Golden Woods Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Golden Woods Phase 2 stands on 1,496 sq m of land (about 0.4 acres), with 3,367 sq m of sanctioned built-up area.
Where can I read reviews of Golden Woods Phase 2?
Google Maps has reviews of Golden Woods Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Golden Woods Phase 2?
Golden Woods Phase 2 by Santosh Kumar Hatte is in Degloor Road, Latur (pincode 413517), near Wadhona, Maharashtra, and is registered on MahaRERA as P52400051653, per GharKundli's check of MahaRERA records.
How many homes are in Golden Woods Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Golden Woods Phase 2 has 40 homes in 2 towers registered on MahaRERA.
When was Golden Woods Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Golden Woods Phase 2 was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Golden Woods Phase 2?
No court cases are listed for Golden Woods Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Golden Woods Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Santosh Kumar Hatte.
Check it yourself on MahaRERA
- How to check the possession date of Golden Woods Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Latur →
Other projects in Udgir
All 4 projects in Udgir (413517) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.