Rajrajeshwari RN Goli Sundarban Phase 1

by SHRI RAJRAJESHWARI DEVELOPERS · Ashok Chowk, Solapur 413007Also near Shelagi, MIDC Solapur, ShivshahiRegistered on MahaRERA as “RN GOLI SUNDARBAN PHASE 1”

What’s in the report? →

Possession date of Rajrajeshwari RN Goli Sundarban Phase 1 (MahaRERA P52600006210): 30 December 2023, and it has already passed. It has 12 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600006210. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52600006210, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about Rajrajeshwari RN Goli Sundarban Phase 1?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Rajrajeshwari RN Goli Sundarban Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600006210
Status
Lapsed (registration period ended)
Builder
SHRI RAJRAJESHWARI DEVELOPERS
Location
Ashok Chowk, Solapur · 413007
Project type
Mixed
Registered on
14 Aug 2017
Completion date at registration
December 2023
Latest completion date
December 2023
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Rajrajeshwari RN Goli Sundarban Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BROWN VILLA100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rajrajeshwari RN Goli Sundarban Phase 1 every 1–2 months.

Rajrajeshwari RN Goli Sundarban Phase 1: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shri R N Goli Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 48 months); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Rajrajeshwari RN Goli Sundarban Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rajrajeshwari RN Goli Sundarban Phase 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Rajrajeshwari RN Goli Sundarban Phase 1

What is the possession date of Rajrajeshwari RN Goli Sundarban Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rajrajeshwari RN Goli Sundarban Phase 1 in Ashok Chowk, Solapur is 30 December 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Rajrajeshwari RN Goli Sundarban Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rajrajeshwari RN Goli Sundarban Phase 1's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Rajrajeshwari RN Goli Sundarban Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rajrajeshwari RN Goli Sundarban Phase 1 in Ashok Chowk, Solapur is P52600006210.

Is Rajrajeshwari RN Goli Sundarban Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1 is registered as P52600006210 and its status is "Lapsed (registration period ended)".

What is the current construction status of Rajrajeshwari RN Goli Sundarban Phase 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BROWN VILLA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Rajrajeshwari RN Goli Sundarban Phase 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Rajrajeshwari RN Goli Sundarban Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1 is registered on MahaRERA as P52600006210, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Rajrajeshwari RN Goli Sundarban Phase 1?

Rajrajeshwari RN Goli Sundarban Phase 1 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Rajrajeshwari RN Goli Sundarban Phase 1?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Rajrajeshwari RN Goli Sundarban Phase 1: gharkundli.com/tools/property-cost-calculator

Has Rajrajeshwari RN Goli Sundarban Phase 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Rajrajeshwari RN Goli Sundarban Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Rajrajeshwari RN Goli Sundarban Phase 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Rajrajeshwari RN Goli Sundarban Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Rajrajeshwari RN Goli Sundarban Phase 1's possession date changes?

The latest dates are on Rajrajeshwari RN Goli Sundarban Phase 1's MahaRERA page (P52600006210). GharKundli's Kundli Watch sends a free WhatsApp update on Rajrajeshwari RN Goli Sundarban Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rajrajeshwari RN Goli Sundarban Phase 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1 has one building filed: BROWN VILLA with 2 floors.

How big is the land of Rajrajeshwari RN Goli Sundarban Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1 stands on 3,353 sq m of land (about 0.8 acres), with 1,070 sq m of sanctioned built-up area.

What is the track record of Rajrajeshwari RN Goli Sundarban Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri R N Goli Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 48 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Rajrajeshwari RN Goli Sundarban Phase 1?

Google Maps has reviews of Rajrajeshwari RN Goli Sundarban Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Rajrajeshwari RN Goli Sundarban Phase 1?

Rajrajeshwari RN Goli Sundarban Phase 1 by SHRI RAJRAJESHWARI DEVELOPERS is in Ashok Chowk, Solapur, pincode 413007 (near Shelagi, MIDC Solapur, Shivshahi), Maharashtra, and is registered on MahaRERA as P52600006210, per GharKundli's check of MahaRERA records. Its land is filed as 8 6. GharKundli lists all 19 MahaRERA projects in Solapur City (413007).

How many flats are in Rajrajeshwari RN Goli Sundarban Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1 has 12 homes in 1 tower registered on MahaRERA.

When was Rajrajeshwari RN Goli Sundarban Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajrajeshwari RN Goli Sundarban Phase 1 was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Rajrajeshwari RN Goli Sundarban Phase 1 have any legal issues or court cases?

No court cases are listed for Rajrajeshwari RN Goli Sundarban Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Rajrajeshwari RN Goli Sundarban Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHRI RAJRAJESHWARI DEVELOPERS.

Other projects in Solapur City (413007)

All 19 projects in Solapur City (413007) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.