Skip to content
GharKundli

Kamtam Icon A Wing

by PRAKASH SHANKAR KAMTAM · New Paccha Peth, Solapur 413006Also near VIP Road, Ashok Chowk

What’s in the report? →

Possession date of Kamtam Icon A Wing (MahaRERA P52600013662): 30 December 2022, moved from 31 March 2018 (57 months later), and it has already passed. It has 16 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600013662. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52600013662, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2022) has passed.

What do you want to know about Kamtam Icon A Wing?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kamtam Icon A Wing has moved

  1. 31 March 2018

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT52600005410)

    Reason the builder gave MahaRERA:
    “we are completed 16 flat ie 4 floors of building and we are applied for occupation certificate to the solapur muncipal corporation. however we are taken the permission from solapur muncipal corporation for 5 th and 6 th floor exiting buildi…” Read the full reason“we are completed 16 flat ie 4 floors of building and we are applied for occupation certificate to the solapur muncipal corporation. however we are taken the permission from solapur muncipal corporation for 5 th and 6 th floor exiting building and addition 1 building on same land. please allow us for the addition to exiting building and new building”
  3. 30 December 2022

    Revised completion date on MahaRERA

Source: Kamtam Icon A Wing’s extension records on MahaRERA (P52600013662), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kamtam Icon A Wing

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600013662
Status
Lapsed (registration period ended)
Builder
PRAKASH SHANKAR KAMTAM
Location
New Paccha Peth, Solapur · 413006
Project type
Residential / Group Housing
Registered on
23 Oct 2017
Completion date at registration
March 2018
Latest completion date
December 2022
Delay so far
57 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Kamtam Icon A Wing, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAMTAM ICON A WING80%100%90%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kamtam Icon A Wing every 1–2 months.

Kamtam Icon A Wing: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Kamtam Icon A Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kamtam Icon A Wing: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kamtam Icon A Wing

What is the possession date of Kamtam Icon A Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kamtam Icon A Wing in New Paccha Peth, Solapur is 30 December 2022 — 57 months later than 31 March 2018, the date given at registration. That date has already passed.

The date has already moved 57 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Kamtam Icon A Wing?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kamtam Icon A Wing's builder has filed on MahaRERA, the official one, is 30 December 2022, already 57 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kamtam Icon A Wing extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing's builder applied to MahaRERA to extend the completion date once: to 31 December 2021, giving the reason "we are completed 16 flat ie 4 floors of building and we are applied for occupation certificate to the solapur muncipal corporation. however we are taken the permission from solapur muncipal corporation for 5 th and 6 th floor exiting building and addition 1 building on same land. please allow us for the addition to exiting building and new building".

What is the RERA number of Kamtam Icon A Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kamtam Icon A Wing in New Paccha Peth, Solapur is P52600013662.

Is Kamtam Icon A Wing registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing is registered as P52600013662 and its status is "Lapsed (registration period ended)".

What is the current construction status of Kamtam Icon A Wing? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KAMTAM ICON A WING is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Kamtam Icon A Wing have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Kamtam Icon A Wing safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing is registered on MahaRERA as P52600013662, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 57 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kamtam Icon A Wing?

Kamtam Icon A Wing isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kamtam Icon A Wing?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kamtam Icon A Wing: gharkundli.com/tools/property-cost-calculator

Has Kamtam Icon A Wing received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Kamtam Icon A Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Kamtam Icon A Wing uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Kamtam Icon A Wing was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kamtam Icon A Wing's possession date changes?

The latest dates are on Kamtam Icon A Wing's MahaRERA page (P52600013662). GharKundli's Kundli Watch sends a free WhatsApp update on Kamtam Icon A Wing every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kamtam Icon A Wing have?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing has one building filed: KAMTAM ICON A WING with 6 floors.

How big is the land of Kamtam Icon A Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing stands on 1,331 sq m of land (about 0.3 acres), with 681 sq m of sanctioned built-up area.

What are the reviews of Kamtam Icon A Wing?

Google Maps has reviews of Kamtam Icon A Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kamtam Icon A Wing?

Kamtam Icon A Wing by PRAKASH SHANKAR KAMTAM is in New Paccha Peth, Solapur, pincode 413006 (near VIP Road, Ashok Chowk), Maharashtra, and is registered on MahaRERA as P52600013662, per GharKundli's check of MahaRERA records. Its land is filed as S NO 154/2/3. GharKundli lists all 34 MahaRERA projects in MIDC Solapur (413006).

How many flats are in Kamtam Icon A Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing has 16 homes in 1 tower registered on MahaRERA.

When was Kamtam Icon A Wing registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kamtam Icon A Wing was registered on MahaRERA on 23 October 2017. GharKundli did not find a title report on the land on file there.

Does Kamtam Icon A Wing have any legal issues or court cases?

No court cases are listed for Kamtam Icon A Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Kamtam Icon A Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRAKASH SHANKAR KAMTAM.

Other projects in MIDC Solapur (413006)

All 34 projects in MIDC Solapur (413006) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.