Kandre Residency
by KANDRE DEVELOPER · Isabavi, Solapur
Possession date of Kandre Residency: 30 April 2027, moved from 30 June 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600026821, and currently active. Its completion date has moved from June 2025 to April 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Kandre Residency?
How the possession date of Kandre Residency has moved
30 June 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA02032620069)
Reason the builder gave MahaRERA:
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of…” Read the full reason
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kandre Residency’s extension records on MahaRERA (P52600026821), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kandre Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600026821
- Status
- Registered and active
- Builder
- KANDRE DEVELOPER
- Location
- Isabavi, Solapur · 413304
- Project type
- Residential / Group Housing
- Registered on
- 28 Oct 2020
- Completion date at registration
- June 2025
- Latest completion date
- April 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 48
- Sold or booked
- 32%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Kandre Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kandre Residency A3 | 100% | 100% | 100% | 100% |
| Kandre Residency A2 | 100% | 100% | 100% | 100% |
| Kandre Residency A4 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Kandre Residency A3: covers 5 floors
- Kandre Residency A2: covers 5 floors
- Kandre Residency A4: covers 5 floors
Latest CC order on MahaRERA: dated 07/08/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kandre Residency every month.
Kandre Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Kandre Residency A3 (5 floors, 23 units) · Kandre Residency A2 (5 floors, 23 units) · Kandre Residency A4 (5 floors, 23 units)
- Car parking: 26 covered
- Land: 2,972 sq m (about 0.7 acres) · sanctioned built-up 2,869 sq m · recreational space 72 sq m
The builder’s record and reviews
Kandre Developer has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.
Read Google reviews of Kandre Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kandre Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kandre Residency
What is the possession date of Kandre Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kandre Residency in Isabavi, Solapur is 30 April 2027 — 18 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Kandre Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kandre Residency's builder has filed on MahaRERA, the official one, is 30 April 2027, already 18 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kandre Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kandre Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kandre Residency in Isabavi, Solapur is P52600026821.
Is Kandre Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency is registered as P52600026821 and its status is "Registered and active".
What is the construction status of Kandre Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Kandre Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kandre Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency is registered on MahaRERA as P52600026821, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Kandre Residency's possession date changes?
The latest dates are on Kandre Residency's MahaRERA page (P52600026821). GharKundli's Kundli Watch sends a free WhatsApp update on Kandre Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kandre Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency has 3 buildings filed: Kandre Residency A3 with 5 floors and 23 units; Kandre Residency A2 with 5 floors and 23 units; Kandre Residency A4 with 5 floors and 23 units.
How much parking does Kandre Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered car parking spaces for Kandre Residency.
How big is the land of Kandre Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency stands on 2,972 sq m of land (about 0.7 acres), with 2,869 sq m of sanctioned built-up area and 72 sq m of recreational open space.
What is the track record of Kandre Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Developer has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Kandre Residency?
Google Maps has reviews of Kandre Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kandre Residency?
Kandre Residency by KANDRE DEVELOPER is in Isabavi, Solapur (pincode 413304), Maharashtra, and is registered on MahaRERA as P52600026821, per GharKundli's check of MahaRERA records.
How many homes are in Kandre Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency has 48 homes in 3 towers registered on MahaRERA, and 32% of them are sold or booked.
When was Kandre Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandre Residency was registered on MahaRERA on 28 October 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on Kandre Residency?
No court cases are listed for Kandre Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Kandre Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KANDRE DEVELOPER, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kandre Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Solapur →
Other projects in Pandharpur
- Aarambha Residency
- STAR AVENEU
- Tirupati Harisha
- HARISAMARTH RESIDENCY
- Kandre's Residency Building No.B2
- KANDRES RESIDENCY A5 BUILDING
- BLOSSOM PARK
- Tirupati Puram II
Other projects by KANDRE DEVELOPER
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.