Golden Tower

by SAMIR WALMIK AHIRE PROPRIETOR OF PALLAVI REALTORS · Indiranagar S.O (Solapur), Solapur

Possession date of Golden Tower: 30 December 2025, moved from 30 December 2024 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52600022854. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Golden Tower?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Golden Tower has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT52600025563)

    Reason the builder gave MahaRERA: “Due to delay in project sanction by Solapur”

Source: Golden Tower’s extension records on MahaRERA (P52600022854), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Golden Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600022854
Status
Lapsed (registration period ended)
Builder
SAMIR WALMIK AHIRE PROPRIETOR OF PALLAVI REALTORS
Location
Indiranagar S.O (Solapur), Solapur · 413004
Project type
Others
Registered on
30 Oct 2019
Completion date at registration
December 2024
Latest completion date
December 2025
Delay so far
12 months
Homes
81
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Golden Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Golden Tower100%100%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Golden Tower every month.

Golden Tower: buildings, flats and land, as filed on MahaRERA

  • Buildings: Golden Tower (9 floors)
  • Land: 1,488 sq m (about 0.4 acres) · sanctioned built-up 2,049 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Golden Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Golden Tower: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Golden Tower

What is the possession date of Golden Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Golden Tower in Indiranagar S.O (Solapur), Solapur is 30 December 2025 — 12 months later than 30 December 2024, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Golden Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Golden Tower's builder has filed on MahaRERA, the official one, is 30 December 2025, already 12 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Golden Tower extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower's builder applied to MahaRERA to extend the completion date once: to 30 December 2025, giving the reason "Due to delay in project sanction by Solapur".

What is the RERA number of Golden Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Golden Tower in Indiranagar S.O (Solapur), Solapur is P52600022854.

Is Golden Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower is registered as P52600022854 and its status is "Lapsed (registration period ended)".

What is the construction status of Golden Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Golden Tower is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Golden Tower have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Golden Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower is registered on MahaRERA as P52600022854, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Golden Tower's possession date changes?

The latest dates are on Golden Tower's MahaRERA page (P52600022854). GharKundli's Kundli Watch sends a free WhatsApp update on Golden Tower every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Golden Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower has one building filed: Golden Tower with 9 floors.

How big is the land of Golden Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower stands on 1,488 sq m of land (about 0.4 acres), with 2,049 sq m of sanctioned built-up area.

Where can I read reviews of Golden Tower?

Google Maps has reviews of Golden Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Golden Tower?

Golden Tower by SAMIR WALMIK AHIRE PROPRIETOR OF PALLAVI REALTORS is in Indiranagar S.O (Solapur), Solapur (pincode 413004), Maharashtra, and is registered on MahaRERA as P52600022854, per GharKundli's check of MahaRERA records.

How many homes are in Golden Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower has 81 homes in 1 tower registered on MahaRERA.

When was Golden Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Golden Tower was registered on MahaRERA on 30 October 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Golden Tower?

No court cases are listed for Golden Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Golden Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMIR WALMIK AHIRE PROPRIETOR OF PALLAVI REALTORS.