Skip to content
GharKundli

PMAY BARSHI NAGAR PARISHAD AHP

by BARSHI NAGAR PARISHAD · Barshi Nagar Parishad, Solapur

Possession date of PMAY BARSHI NAGAR PARISHAD AHP: 30 January 2027, moved from 31 December 2025 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600047436, and currently active. Its completion date has moved from December 2025 to January 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PMAY BARSHI NAGAR PARISHAD AHP?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PMAY BARSHI NAGAR PARISHAD AHP has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 September 2026

    Extended at the builder's request (MahaRERA application EA29042620778)

    Reason the builder gave MahaRERA:
    “We respectfully submit that the construction of the above-mentioned project is presently under progress. However, the project could not be completed within the stipulated timeline i.e., December 2025, due to the following unavoidable circum…” Read the full reason“We respectfully submit that the construction of the above-mentioned project is presently under progress. However, the project could not be completed within the stipulated timeline i.e., December 2025, due to the following unavoidable circumstances beyond our control: 1. Drought Conditions (2023–24): The project was adversely affected due to severe drought conditions prevailing during the year 2023–24, resulting in a slowdown of construction activities for approximately four months. 2. Technical Issues on PMAY Portal: Due to issues relating to gender correction on the PMAY portal, we were un…”
  3. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PMAY BARSHI NAGAR PARISHAD AHP’s extension records on MahaRERA (P52600047436), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PMAY BARSHI NAGAR PARISHAD AHP

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600047436
Status
Registered and active
Builder
BARSHI NAGAR PARISHAD
Location
Barshi Nagar Parishad, Solapur · 413401
Project type
Residential / Group Housing
Registered on
31 Oct 2022
Completion date at registration
December 2025
Latest completion date
January 2027
Delay so far
9 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
1,603
Sold or booked
10%
Towers
31
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of PMAY BARSHI NAGAR PARISHAD AHP, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B1 / B1100%100%100%0%
B2 / B2100%0%0%0%
B3 / B3100%0%0%0%
B4 / B4100%0%0%0%
B5 / B5100%0%0%0%
B6 / B6100%0%0%0%
B7 / B7100%0%0%0%
B8 / B8100%0%0%0%
B9 / B9100%0%0%0%
B10 / B10100%0%0%0%
B11 / B11100%0%0%0%
B12 / B12100%0%0%0%
B13 / B13100%0%0%0%
B14 / B14100%0%0%0%
B15 / B15100%0%0%0%
B16 / B16100%20%20%0%
B17 / B17100%0%0%0%
B18 / B18100%50%50%0%
B19 / B19100%100%100%0%
B20 / B20100%100%100%0%
B21 / B21100%100%100%50%
B22 / B22100%100%100%50%
B23 / B23100%100%100%50%
B24 / B24100%100%100%50%
B25 / B25100%100%100%50%
B26 / B26100%100%100%50%
B27 / B270%0%0%0%
DRIVER ROOMS0%0%0%0%
SANETARY BLOCK0%0%0%0%
PRIMARY SCHOOL0%0%0%0%

Showing 30 of 31 towers.

Commencement certificate (CC), as filed on MahaRERA

  • B1: covers 5 floors
  • B2: covers 5 floors
  • B3: covers 5 floors
  • B4: covers 5 floors
  • B5: covers 5 floors
  • B6: covers 5 floors
  • B7: covers 5 floors
  • B8: covers 5 floors
  • B9: covers 5 floors
  • B10: covers 5 floors
  • B11: covers 5 floors
  • B12: covers 5 floors
  • B13: covers 5 floors
  • B14: covers 5 floors
  • B15: covers 5 floors
  • B16: covers 5 floors
  • B17: covers 5 floors
  • B18: covers 5 floors
  • B19: covers 5 floors
  • B20: covers 5 floors
  • B21: covers 5 floors
  • B22: covers 5 floors
  • B23: covers 5 floors
  • B24: covers 5 floors
  • B25: covers 5 floors
  • B26: covers 5 floors
  • B27: covers 5 floors
  • DRIVER ROOMS: covers 1 floors
  • SANETARY BLOCK: covers 1 floors
  • PRIMARY SCHOOL: covers 1 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PMAY BARSHI NAGAR PARISHAD AHP every month.

PMAY BARSHI NAGAR PARISHAD AHP: buildings, flats and land, as filed on MahaRERA

  • Buildings: B1 (5 floors, 60 units) · B2 (5 floors, 60 units) · B3 (5 floors, 61 units) · B4 (5 floors, 60 units) · B5 (5 floors, 60 units) · B6 (5 floors, 60 units) · B7 (5 floors, 60 units) · B8 (5 floors, 60 units) · and 22 more
  • Land: 57,354 sq m (about 14.2 acres) · sanctioned built-up 1,87,568 sq m · recreational space 5,736 sq m
  • Boundaries filed include: PIMPALGAON DHAS 30MTR ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PMAY BARSHI NAGAR PARISHAD AHP →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PMAY BARSHI NAGAR PARISHAD AHP: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PMAY BARSHI NAGAR PARISHAD AHP

What is the possession date of PMAY BARSHI NAGAR PARISHAD AHP?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PMAY BARSHI NAGAR PARISHAD AHP in Barshi Nagar Parishad, Solapur is 30 January 2027 — 9 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PMAY BARSHI NAGAR PARISHAD AHP?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PMAY BARSHI NAGAR PARISHAD AHP's builder has filed on MahaRERA, the official one, is 30 January 2027, already 9 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PMAY BARSHI NAGAR PARISHAD AHP extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "We respectfully submit that the construction of the above-mentioned project is presently under progress. However, the project could not be completed within the stipulated timeline i.e., December 2025, due to the following unavoidable circumstances beyond our control: 1. Drought Conditions (2023–24): The project was adversely affected due to severe drought conditions prevailing during the year 2023–24, resulting in a slowdown of construction activities for approximately four months. 2. Technical Issues on PMAY Portal: Due to issues relating to gender correction on the PMAY portal, we were un…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of PMAY BARSHI NAGAR PARISHAD AHP?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PMAY BARSHI NAGAR PARISHAD AHP in Barshi Nagar Parishad, Solapur is P52600047436.

Is PMAY BARSHI NAGAR PARISHAD AHP registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP is registered as P52600047436 and its status is "Registered and active".

What is the construction status of PMAY BARSHI NAGAR PARISHAD AHP?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does PMAY BARSHI NAGAR PARISHAD AHP have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is PMAY BARSHI NAGAR PARISHAD AHP safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP is registered on MahaRERA as P52600047436, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PMAY BARSHI NAGAR PARISHAD AHP's possession date changes?

The latest dates are on PMAY BARSHI NAGAR PARISHAD AHP's MahaRERA page (P52600047436). GharKundli's Kundli Watch sends a free WhatsApp update on PMAY BARSHI NAGAR PARISHAD AHP every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PMAY BARSHI NAGAR PARISHAD AHP have?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP has 30 buildings filed: B1 with 5 floors and 60 units; B2 with 5 floors and 60 units; B3 with 5 floors and 61 units; B4 with 5 floors and 60 units; B5 with 5 floors and 60 units; B6 with 5 floors and 60 units; and 24 more.

How big is the land of PMAY BARSHI NAGAR PARISHAD AHP?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP stands on 57,354 sq m of land (about 14.2 acres), with 1,87,568 sq m of sanctioned built-up area and 5,736 sq m of recreational open space.

Where can I read reviews of PMAY BARSHI NAGAR PARISHAD AHP?

Google Maps has reviews of PMAY BARSHI NAGAR PARISHAD AHP written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PMAY BARSHI NAGAR PARISHAD AHP?

PMAY BARSHI NAGAR PARISHAD AHP by BARSHI NAGAR PARISHAD is in Barshi Nagar Parishad, Solapur (pincode 413401), Maharashtra, and is registered on MahaRERA as P52600047436, per GharKundli's check of MahaRERA records. Its boundaries filed there include PIMPALGAON DHAS 30MTR ROAD.

How many homes are in PMAY BARSHI NAGAR PARISHAD AHP?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP has 1,603 homes in 31 towers registered on MahaRERA, and 10% of them are sold or booked.

When was PMAY BARSHI NAGAR PARISHAD AHP registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PMAY BARSHI NAGAR PARISHAD AHP was registered on MahaRERA on 31 October 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on PMAY BARSHI NAGAR PARISHAD AHP?

No court cases are listed for PMAY BARSHI NAGAR PARISHAD AHP on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PMAY BARSHI NAGAR PARISHAD AHP?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BARSHI NAGAR PARISHAD.

All projects with possession due in 2027 in Solapur →

Other projects in pincode 413401

All 11 projects in Barshi (413401) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.