AYASHA PLAZA

by ARSH CONSTRUCTION · Guhagar, Ratnagiri

Possession date of AYASHA PLAZA: 31 December 2023, moved from 31 December 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52800034193. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about AYASHA PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AYASHA PLAZA has moved

  1. 31 December 2022

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52800013701)

    Reason the builder gave MahaRERA: “NON AVAILABILITY OF SAND AND OTHER BUILDING MATERIAL SUPPLIES,”

Source: AYASHA PLAZA’s extension records on MahaRERA (P52800034193), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AYASHA PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800034193
Status
Lapsed (registration period ended)
Builder
ARSH CONSTRUCTION
Location
Guhagar, Ratnagiri · 415724
Project type
Others
Registered on
25 Mar 2022
Completion date at registration
December 2022
Latest completion date
December 2023
Delay so far
12 months
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of AYASHA PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AYASHA PLAZA100%100%35%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AYASHA PLAZA every month.

AYASHA PLAZA: buildings, flats and land, as filed on MahaRERA

  • Buildings: AYASHA PLAZA (4 floors)
  • Land: 450 sq m (about 0.1 acres) · sanctioned built-up 380 sq m · recreational space 380 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AYASHA PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AYASHA PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AYASHA PLAZA

What is the possession date of AYASHA PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for AYASHA PLAZA in Guhagar, Ratnagiri is 31 December 2023 — 12 months later than 31 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for AYASHA PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AYASHA PLAZA's builder has filed on MahaRERA, the official one, is 31 December 2023, already 12 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AYASHA PLAZA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA's builder applied to MahaRERA to extend the completion date once: to 31 December 2023, giving the reason "NON AVAILABILITY OF SAND AND OTHER BUILDING MATERIAL SUPPLIES,".

What is the RERA number of AYASHA PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of AYASHA PLAZA in Guhagar, Ratnagiri is P52800034193.

Is AYASHA PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA is registered as P52800034193 and its status is "Lapsed (registration period ended)".

What is the construction status of AYASHA PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on AYASHA PLAZA is 100% done and internal work 35%. GharKundli's full report compares construction progress with the deadline.

Does AYASHA PLAZA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is AYASHA PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA is registered on MahaRERA as P52800034193, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AYASHA PLAZA's possession date changes?

The latest dates are on AYASHA PLAZA's MahaRERA page (P52800034193). GharKundli's Kundli Watch sends a free WhatsApp update on AYASHA PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AYASHA PLAZA have?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA has one building filed: AYASHA PLAZA with 4 floors.

How big is the land of AYASHA PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA stands on 450 sq m of land (about 0.1 acres), with 380 sq m of sanctioned built-up area and 380 sq m of recreational open space.

Where can I read reviews of AYASHA PLAZA?

Google Maps has reviews of AYASHA PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AYASHA PLAZA?

AYASHA PLAZA by ARSH CONSTRUCTION is in Guhagar, Ratnagiri (pincode 415724), Maharashtra, and is registered on MahaRERA as P52800034193, per GharKundli's check of MahaRERA records.

How many homes are in AYASHA PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA has 12 homes in 1 tower registered on MahaRERA.

When was AYASHA PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), AYASHA PLAZA was registered on MahaRERA on 25 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on AYASHA PLAZA?

No court cases are listed for AYASHA PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of AYASHA PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ARSH CONSTRUCTION, which has 1 other project registered on MahaRERA.