by VEDANT DEVELOPERS · Banda, Sindhudurg

Possession date of PARVATI PRIDE: 28 November 2024, moved from 28 May 2021 (42 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52900016208. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (November 2024) has passed.

What do you want to know about PARVATI PRIDE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PARVATI PRIDE has moved

  1. 28 May 2021

    Completion date given when the project was registered

  2. 28 May 2022

    Extended at the builder's request (MahaRERA application EXT52900009572)

    Reason the builder gave MahaRERA: “LOCKDOWN”
  3. 28 November 2023

    Extended at the builder's request (MahaRERA application EXT52900012839)

    Reason the builder gave MahaRERA: “Various Reasons such as Weather, Equipment Failures, Labour Shortages and for Some Extra Work.”
  4. 28 November 2024

    Extended at the builder's request (MahaRERA application EXT52900018021)

    Reason the builder gave MahaRERA: “REVISED APPROVAL FROM TOWN PLANING AUTHORITY ,SINDUDURGA PENDING .”

Source: PARVATI PRIDE’s extension records on MahaRERA (P52900016208), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PARVATI PRIDE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900016208
Status
Lapsed (registration period ended)
Builder
VEDANT DEVELOPERS
Location
Banda, Sindhudurg · 416511
Project type
Residential / Group Housing
Registered on
24 Apr 2018
Completion date at registration
May 2021
Latest completion date
November 2024
Delay so far
42 months
Homes
23
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of PARVATI PRIDE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PARVATI PRIDE100%100%100%85%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARVATI PRIDE every month.

PARVATI PRIDE: buildings, flats and land, as filed on MahaRERA

  • Buildings: PARVATI PRIDE (4 floors)
  • Land: 830 sq m (about 0.2 acres) · sanctioned built-up 520 sq m · recreational space 408 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PARVATI PRIDE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PARVATI PRIDE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PARVATI PRIDE

What is the possession date of PARVATI PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PARVATI PRIDE in Banda, Sindhudurg is 28 November 2024 — 42 months later than 28 May 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PARVATI PRIDE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PARVATI PRIDE's builder has filed on MahaRERA, the official one, is 28 November 2024, already 42 months later than the 28 May 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PARVATI PRIDE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE's builder applied to MahaRERA to extend the completion date 3 times: to 28 May 2022, giving the reason "LOCKDOWN"; to 28 November 2023, giving the reason "Various Reasons such as Weather, Equipment Failures, Labour Shortages and for Some Extra Work."; to 28 November 2024, giving the reason "REVISED APPROVAL FROM TOWN PLANING AUTHORITY ,SINDUDURGA PENDING .".

What is the RERA number of PARVATI PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PARVATI PRIDE in Banda, Sindhudurg is P52900016208.

Is PARVATI PRIDE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE is registered as P52900016208 and its status is "Lapsed (registration period ended)".

What is the construction status of PARVATI PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PARVATI PRIDE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does PARVATI PRIDE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is PARVATI PRIDE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE is registered on MahaRERA as P52900016208, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PARVATI PRIDE's possession date changes?

The latest dates are on PARVATI PRIDE's MahaRERA page (P52900016208). GharKundli's Kundli Watch sends a free WhatsApp update on PARVATI PRIDE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PARVATI PRIDE have?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE has one building filed: PARVATI PRIDE with 4 floors.

How big is the land of PARVATI PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE stands on 830 sq m of land (about 0.2 acres), with 520 sq m of sanctioned built-up area and 408 sq m of recreational open space.

Where can I read reviews of PARVATI PRIDE?

Google Maps has reviews of PARVATI PRIDE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PARVATI PRIDE?

PARVATI PRIDE by VEDANT DEVELOPERS is in Banda, Sindhudurg (pincode 416511), Maharashtra, and is registered on MahaRERA as P52900016208, per GharKundli's check of MahaRERA records.

How many homes are in PARVATI PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE has 23 homes in 1 tower registered on MahaRERA.

When was PARVATI PRIDE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATI PRIDE was registered on MahaRERA on 24 April 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on PARVATI PRIDE?

No court cases are listed for PARVATI PRIDE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PARVATI PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VEDANT DEVELOPERS, which has 9 other projects registered on MahaRERA.