DYANESHWARI

by DYANESHWARI ENTERPRISES · Kudal, SindhudurgAlso near Industrial Area Pinguli

Possession date of DYANESHWARI: 30 September 2023, moved from 30 September 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52900031622. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (September 2023) has passed.

What do you want to know about DYANESHWARI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DYANESHWARI has moved

  1. 30 September 2022

    Completion date given when the project was registered

  2. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT52900013924)

    Reason the builder gave MahaRERA: “Due to Health and liquidity issue Project Completion Delay.”

Source: DYANESHWARI’s extension records on MahaRERA (P52900031622), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DYANESHWARI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900031622
Status
Lapsed (registration period ended)
Builder
DYANESHWARI ENTERPRISES
Location
Kudal, Sindhudurg · 416520
Project type
Commercial
Registered on
3 Nov 2021
Completion date at registration
September 2022
Latest completion date
September 2023
Delay so far
12 months
Homes
15
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of DYANESHWARI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DYANESHWARI100%100%90%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DYANESHWARI every month.

DYANESHWARI: buildings, flats and land, as filed on MahaRERA

  • Buildings: DYANESHWARI (7 floors)
  • Land: 610 sq m (about 0.2 acres) · sanctioned built-up 656 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of DYANESHWARI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DYANESHWARI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DYANESHWARI

What is the possession date of DYANESHWARI?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DYANESHWARI in Kudal, Sindhudurg is 30 September 2023 — 12 months later than 30 September 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for DYANESHWARI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DYANESHWARI's builder has filed on MahaRERA, the official one, is 30 September 2023, already 12 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DYANESHWARI extended?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI's builder applied to MahaRERA to extend the completion date once: to 30 September 2023, giving the reason "Due to Health and liquidity issue Project Completion Delay.".

What is the RERA number of DYANESHWARI?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DYANESHWARI in Kudal, Sindhudurg is P52900031622.

Is DYANESHWARI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI is registered as P52900031622 and its status is "Lapsed (registration period ended)".

What is the construction status of DYANESHWARI?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on DYANESHWARI is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does DYANESHWARI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is DYANESHWARI safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI is registered on MahaRERA as P52900031622, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DYANESHWARI's possession date changes?

The latest dates are on DYANESHWARI's MahaRERA page (P52900031622). GharKundli's Kundli Watch sends a free WhatsApp update on DYANESHWARI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DYANESHWARI have?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI has one building filed: DYANESHWARI with 7 floors.

How big is the land of DYANESHWARI?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI stands on 610 sq m of land (about 0.2 acres), with 656 sq m of sanctioned built-up area.

Where can I read reviews of DYANESHWARI?

Google Maps has reviews of DYANESHWARI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DYANESHWARI?

DYANESHWARI by DYANESHWARI ENTERPRISES is in Kudal, Sindhudurg (pincode 416520), near Industrial Area Pinguli, Maharashtra, and is registered on MahaRERA as P52900031622, per GharKundli's check of MahaRERA records.

How many homes are in DYANESHWARI?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI has 15 homes in 1 tower registered on MahaRERA.

When was DYANESHWARI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DYANESHWARI was registered on MahaRERA on 3 November 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on DYANESHWARI?

No court cases are listed for DYANESHWARI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of DYANESHWARI?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DYANESHWARI ENTERPRISES.

Other projects in pincode 416520

All 37 projects in Kudal (416520) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.