Nirmitee Avighna
by NIRMITEE BUILDERS & DEVELOPERS · Near Topiwala Vachanalay, SindhudurgAlso near Kudal
Possession date of Nirmitee Avighna: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900049381, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Nirmitee Avighna?
How the possession date of Nirmitee Avighna has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Nirmitee Avighna’s extension records on MahaRERA (P52900049381), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nirmitee Avighna
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900049381
- Status
- Registered and active
- Builder
- NIRMITEE BUILDERS & DEVELOPERS
- Location
- Near Topiwala Vachanalay, Sindhudurg · 416520
- Project type
- Residential / Group Housing
- Registered on
- 7 Feb 2023
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 151
- Sold or booked
- 41%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Nirmitee Avighna, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Nirmitee Avighna | 100% | 100% | 90% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Nirmitee Avighna: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nirmitee Avighna every month.
Nirmitee Avighna: buildings, flats and land, as filed on MahaRERA
- Buildings: Nirmitee Avighna (11 floors, 153 units)
- Car parking: 25 covered, 4 open
- Land: 3,309 sq m (about 0.8 acres) · sanctioned built-up 9,274 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Nirmitee Avighna →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nirmitee Avighna: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Nirmitee Avighna
What is the possession date of Nirmitee Avighna?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nirmitee Avighna in Near Topiwala Vachanalay, Sindhudurg is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Nirmitee Avighna?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirmitee Avighna's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Nirmitee Avighna?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nirmitee Avighna in Near Topiwala Vachanalay, Sindhudurg is P52900049381.
Is Nirmitee Avighna registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmitee Avighna is registered as P52900049381 and its status is "Registered and active".
What is the construction status of Nirmitee Avighna?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmitee Avighna's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Nirmitee Avighna is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Nirmitee Avighna have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Nirmitee Avighna safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmitee Avighna is registered on MahaRERA as P52900049381, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Nirmitee Avighna's possession date changes?
The latest dates are on Nirmitee Avighna's MahaRERA page (P52900049381). GharKundli's Kundli Watch sends a free WhatsApp update on Nirmitee Avighna every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nirmitee Avighna have?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmitee Avighna has one building filed: Nirmitee Avighna with 11 floors and 153 units.
How much parking does Nirmitee Avighna have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 25 covered and 4 open car parking spaces for Nirmitee Avighna.
How big is the land of Nirmitee Avighna?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmitee Avighna stands on 3,309 sq m of land (about 0.8 acres), with 9,274 sq m of sanctioned built-up area.
Where can I read reviews of Nirmitee Avighna?
Google Maps has reviews of Nirmitee Avighna written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Nirmitee Avighna?
Nirmitee Avighna by NIRMITEE BUILDERS & DEVELOPERS is in Near Topiwala Vachanalay, Sindhudurg (pincode 416520), near Kudal, Maharashtra, and is registered on MahaRERA as P52900049381, per GharKundli's check of MahaRERA records.
How many homes are in Nirmitee Avighna?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmitee Avighna has 151 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.
When was Nirmitee Avighna registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmitee Avighna was registered on MahaRERA on 7 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Nirmitee Avighna?
No court cases are listed for Nirmitee Avighna on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Nirmitee Avighna?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NIRMITEE BUILDERS & DEVELOPERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Nirmitee Avighna
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kudal
Other projects by NIRMITEE BUILDERS & DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.