Patil Parbat Plaza
by Vijaysinh Krishnarao Parbat · Vidyanagar, Sangli
Possession date of Patil Parbat Plaza: 9 August 2024, moved from 9 February 2022 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P53100015694. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (August 2024) has passed.
What do you want to know about Patil Parbat Plaza?
How the possession date of Patil Parbat Plaza has moved
9 February 2022
Completion date given when the project was registered
9 August 2024
Extended at the builder's request (MahaRERA application EXT53100011686)
Reason the builder gave MahaRERA:
“Dear Sir, I, Ashutosh Patil, am a doctor by profession. I had started this project in my city. But soon after starting the same Covid 19 situation arouse in our state & city. Due to which, I was unable to alocate time & efforts for the same…” Read the full reason
“Dear Sir, I, Ashutosh Patil, am a doctor by profession. I had started this project in my city. But soon after starting the same Covid 19 situation arouse in our state & city. Due to which, I was unable to alocate time & efforts for the same. Post getting building permission I havent started consturction work, nor did receive any bookings against the units. I request you to kindly consider my case. Thanks”
Source: Patil Parbat Plaza’s extension records on MahaRERA (P53100015694), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Patil Parbat Plaza
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100015694
- Status
- Lapsed (registration period ended)
- Builder
- Vijaysinh Krishnarao Parbat
- Location
- Vidyanagar, Sangli · 416310
- Project type
- Residential / Group Housing
- Registered on
- 16 Mar 2018
- Completion date at registration
- February 2022
- Latest completion date
- August 2024
- Delay so far
- 30 months
- Homes
- 20
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Patil Parbat Plaza, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI-LAXMAN RESIDENCY | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Patil Parbat Plaza every month.
Patil Parbat Plaza: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI-LAXMAN RESIDENCY (9 floors)
- Land: 979 sq m (about 0.2 acres) · sanctioned built-up 1,478 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Vijaysinha Krishnarao Parbat has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Patil Parbat Plaza →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Patil Parbat Plaza: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Patil Parbat Plaza
What is the possession date of Patil Parbat Plaza?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Patil Parbat Plaza in Vidyanagar, Sangli is 9 August 2024 — 30 months later than 9 February 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Patil Parbat Plaza?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Patil Parbat Plaza's builder has filed on MahaRERA, the official one, is 9 August 2024, already 30 months later than the 9 February 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Patil Parbat Plaza extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza's builder applied to MahaRERA to extend the completion date once: to 9 August 2024, giving the reason "Dear Sir, I, Ashutosh Patil, am a doctor by profession. I had started this project in my city. But soon after starting the same Covid 19 situation arouse in our state & city. Due to which, I was unable to alocate time & efforts for the same. Post getting building permission I havent started consturction work, nor did receive any bookings against the units. I request you to kindly consider my case. Thanks".
What is the RERA number of Patil Parbat Plaza?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Patil Parbat Plaza in Vidyanagar, Sangli is P53100015694.
Is Patil Parbat Plaza registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza is registered as P53100015694 and its status is "Lapsed (registration period ended)".
What is the construction status of Patil Parbat Plaza?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI-LAXMAN RESIDENCY is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Patil Parbat Plaza have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Patil Parbat Plaza safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza is registered on MahaRERA as P53100015694, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Patil Parbat Plaza's possession date changes?
The latest dates are on Patil Parbat Plaza's MahaRERA page (P53100015694). GharKundli's Kundli Watch sends a free WhatsApp update on Patil Parbat Plaza every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Patil Parbat Plaza have?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza has one building filed: SAI-LAXMAN RESIDENCY with 9 floors.
How big is the land of Patil Parbat Plaza?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza stands on 979 sq m of land (about 0.2 acres), with 1,478 sq m of sanctioned built-up area.
What is the track record of Patil Parbat Plaza's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Vijaysinha Krishnarao Parbat has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Patil Parbat Plaza?
Google Maps has reviews of Patil Parbat Plaza written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Patil Parbat Plaza?
Patil Parbat Plaza by Vijaysinh Krishnarao Parbat is in Vidyanagar, Sangli (pincode 416310), Maharashtra, and is registered on MahaRERA as P53100015694, per GharKundli's check of MahaRERA records.
How many homes are in Patil Parbat Plaza?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza has 20 homes in 1 tower registered on MahaRERA.
When was Patil Parbat Plaza registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Patil Parbat Plaza was registered on MahaRERA on 16 March 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Patil Parbat Plaza?
No court cases are listed for Patil Parbat Plaza on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Patil Parbat Plaza?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vijaysinh Krishnarao Parbat.
Check it yourself on MahaRERA
- How to check the possession date of Patil Parbat Plaza
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Palus
- MAHANKALI HEIGHTS PHASE VII
- INDIRA GOPAL
- SHIVTARA APARTMENT
- RAJ TOWERS
- Satpute Parbat Plaza
- NEW JADHAV COMPLEX
- Nisarg City Phase 1
- SUN RAYS ESTATE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.