City Center Complex

by MAHEBOOBALI MAHMMADGOUS MANER · Miraj, Sangli 416410Also near District Court Sangli

What’s in the report? →

Possession date of City Center Complex (MahaRERA P53100020365): 9 November 2021, moved from 10 November 2020 (12 months later), and it has already passed. It has 18 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P53100020365. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P53100020365, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (November 2021) has passed.

What do you want to know about City Center Complex?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of City Center Complex has moved

  1. 10 November 2020

    Completion date given when the project was registered

  2. 9 May 2021

    Extended at the builder's request (MahaRERA application EXT53100009278)

    Reason the builder gave MahaRERA: “PROJECT EXTENTION BECAUSE LOCKDOWN & COVID 19”
  3. 9 November 2021

    Revised completion date on MahaRERA

Source: City Center Complex’s extension records on MahaRERA (P53100020365), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on City Center Complex

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100020365
Status
Lapsed (registration period ended)
Builder
MAHEBOOBALI MAHMMADGOUS MANER
Location
Miraj, Sangli · 416410
Project type
Residential / Group Housing
Registered on
9 Apr 2019
Completion date at registration
November 2020
Latest completion date
November 2021
Delay so far
12 months
Homes
18
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of City Center Complex, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CITY CENTER COMPLEX0%60%5%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on City Center Complex every 1–2 months.

City Center Complex: buildings, flats and land, as filed on MahaRERA

  • Buildings: CITY CENTER COMPLEX (7 floors)
  • Land: 379 sq m (about 0.1 acres) · sanctioned built-up 743 sq m
  • Land, as filed: C.S. NO. 5636,5736
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of City Center Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

City Center Complex: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about City Center Complex

What is the possession date of City Center Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for City Center Complex in Miraj, Sangli is 9 November 2021 — 12 months later than 10 November 2020, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for City Center Complex?

Builders and listing sites often quote an earlier "target" date for handover. The completion date City Center Complex's builder has filed on MahaRERA, the official one, is 9 November 2021, already 12 months later than the 10 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of City Center Complex extended?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex's builder applied to MahaRERA to extend the completion date once: to 9 May 2021, giving the reason "PROJECT EXTENTION BECAUSE LOCKDOWN & COVID 19".

What is the RERA number of City Center Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of City Center Complex in Miraj, Sangli is P53100020365.

Is City Center Complex registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex is registered as P53100020365 and its status is "Lapsed (registration period ended)".

What is the current construction status of City Center Complex? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on CITY CENTER COMPLEX is 60% done and internal work 5%. GharKundli's full report compares construction progress with the deadline.

Does City Center Complex have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is City Center Complex safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex is registered on MahaRERA as P53100020365, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in City Center Complex?

City Center Complex isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in City Center Complex?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in City Center Complex: gharkundli.com/tools/property-cost-calculator

Has City Center Complex received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 9 November 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for City Center Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (9 November 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has City Center Complex uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for City Center Complex was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if City Center Complex's possession date changes?

The latest dates are on City Center Complex's MahaRERA page (P53100020365). GharKundli's Kundli Watch sends a free WhatsApp update on City Center Complex every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does City Center Complex have?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex has one building filed: CITY CENTER COMPLEX with 7 floors.

How big is the land of City Center Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex stands on 379 sq m of land (about 0.1 acres), with 743 sq m of sanctioned built-up area.

What are the reviews of City Center Complex?

Google Maps has reviews of City Center Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of City Center Complex?

City Center Complex by MAHEBOOBALI MAHMMADGOUS MANER is in Miraj, Sangli, pincode 416410 (near District Court Sangli), Maharashtra, and is registered on MahaRERA as P53100020365, per GharKundli's check of MahaRERA records. Its land is filed as C.S. NO. 5636,5736. GharKundli lists all 111 MahaRERA projects in Miraj (416410).

How many flats are in City Center Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex has 18 homes in 1 tower registered on MahaRERA.

When was City Center Complex registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), City Center Complex was registered on MahaRERA on 9 April 2019. GharKundli did not find a title report on the land on file there.

Does City Center Complex have any legal issues or court cases?

No court cases are listed for City Center Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of City Center Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHEBOOBALI MAHMMADGOUS MANER.