ARIHANT CAPITAL
by ARIHANT DEVELOPERS · Vijaynagar, SangliAlso near Kupwad
Possession date of ARIHANT CAPITAL: 25 December 2026, moved from 29 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100019171, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ARIHANT CAPITAL?
How the possession date of ARIHANT CAPITAL has moved
29 December 2023
Completion date given when the project was registered
25 December 2024
Extended at the builder's request (MahaRERA application EXT53100018298)
Reason the builder gave MahaRERA: “DUE TO LOW BOOKING BECAUSE INTEREST RATE HIGH & LABOUR AND MATERIAL COST IS INCREASE .”
25 December 2025
Extended at the builder's request (MahaRERA application EXT53100027965)
Reason the builder gave MahaRERA: “LOCKDOWN RATE HIKE OF MATERIAL AND LABOUR BOOKING SLOW DETAILS REASON ATTACHED SEPRATLY”
25 December 2026
Extended at the builder's request (MahaRERA application EA16032620235)
Reason the builder gave MahaRERA: “Due To Material Shortage , Labor Shortage , Slow Booking due to Corona & Flood ,”
Source: ARIHANT CAPITAL’s extension records on MahaRERA (P53100019171), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ARIHANT CAPITAL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100019171
- Status
- Registered and active
- Builder
- ARIHANT DEVELOPERS
- Location
- Vijaynagar, Sangli · 416416
- Project type
- Others
- Registered on
- 9 Jan 2019
- Completion date at registration
- December 2023
- Latest completion date
- December 2026
- Delay so far
- 36 months
- Homes
- 12
- Sold or booked
- 50%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of ARIHANT CAPITAL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ARIHANT CAPITAL | 100% | 100% | 95% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- ARIHANT CAPITAL: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT CAPITAL every month.
ARIHANT CAPITAL: buildings, flats and land, as filed on MahaRERA
- Buildings: ARIHANT CAPITAL (7 floors, 30 units)
- Car parking: 2 open
- Land: 580 sq m (about 0.1 acres) · sanctioned built-up 1,083 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ARIHANT CAPITAL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARIHANT CAPITAL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARIHANT CAPITAL
What is the possession date of ARIHANT CAPITAL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT CAPITAL in Vijaynagar, Sangli is 25 December 2026 — 36 months later than 29 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ARIHANT CAPITAL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT CAPITAL's builder has filed on MahaRERA, the official one, is 25 December 2026, already 36 months later than the 29 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ARIHANT CAPITAL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL's builder applied to MahaRERA to extend the completion date 3 times: to 25 December 2024, giving the reason "DUE TO LOW BOOKING BECAUSE INTEREST RATE HIGH & LABOUR AND MATERIAL COST IS INCREASE ."; to 25 December 2025, giving the reason "LOCKDOWN RATE HIKE OF MATERIAL AND LABOUR BOOKING SLOW DETAILS REASON ATTACHED SEPRATLY"; to 25 December 2026, giving the reason "Due To Material Shortage , Labor Shortage , Slow Booking due to Corona & Flood ,".
What is the RERA number of ARIHANT CAPITAL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT CAPITAL in Vijaynagar, Sangli is P53100019171.
Is ARIHANT CAPITAL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL is registered as P53100019171 and its status is "Registered and active".
What is the construction status of ARIHANT CAPITAL?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ARIHANT CAPITAL is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does ARIHANT CAPITAL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ARIHANT CAPITAL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL is registered on MahaRERA as P53100019171, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ARIHANT CAPITAL's possession date changes?
The latest dates are on ARIHANT CAPITAL's MahaRERA page (P53100019171). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT CAPITAL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARIHANT CAPITAL have?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL has one building filed: ARIHANT CAPITAL with 7 floors and 30 units.
How much parking does ARIHANT CAPITAL have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 2 open car parking spaces for ARIHANT CAPITAL.
How big is the land of ARIHANT CAPITAL?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL stands on 580 sq m of land (about 0.1 acres), with 1,083 sq m of sanctioned built-up area.
Where can I read reviews of ARIHANT CAPITAL?
Google Maps has reviews of ARIHANT CAPITAL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARIHANT CAPITAL?
ARIHANT CAPITAL by ARIHANT DEVELOPERS is in Vijaynagar, Sangli (pincode 416416), near Kupwad, Maharashtra, and is registered on MahaRERA as P53100019171, per GharKundli's check of MahaRERA records.
How many homes are in ARIHANT CAPITAL?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL has 12 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.
When was ARIHANT CAPITAL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CAPITAL was registered on MahaRERA on 9 January 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on ARIHANT CAPITAL?
No court cases are listed for ARIHANT CAPITAL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ARIHANT CAPITAL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT DEVELOPERS, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ARIHANT CAPITAL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Sangli →
Other projects in Vijaynagar
All 134 projects in Sangli (416416) →Other projects by ARIHANT DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.