Possession: SHREE SIDDHIVINAYAK HEIGHTS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P53100027420. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHREE SIDDHIVINAYAK HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE SIDDHIVINAYAK HEIGHTS has moved

  1. 1 June 2023

    Completion date given when the project was registered

  2. 30 May 2024

    Extended at the builder's request (MahaRERA application EXT53100017050)

    Reason the builder gave MahaRERA:
    “Respected Sir/Madam, I am writing on behalf of Suryapratap Promoters and Developers, the developer responsible for the construction of the "Siddhivinayak Heights" project located at Vita, Sangli. We would like to bring to your attention the…” Read the full reason“Respected Sir/Madam, I am writing on behalf of Suryapratap Promoters and Developers, the developer responsible for the construction of the "Siddhivinayak Heights" project located at Vita, Sangli. We would like to bring to your attention the reasons for the delay in completing the construction and request an extension of the completion date until 30th May 2024. The delay in the completion of the project can be attributed to two significant factors, which have severely impacted our construction timeline: 1. Non-availability of CEO, Vita Municipal Council for approving sanctioned plan: Due to…”
  3. 30 November 2024

    Extended at the builder's request (MahaRERA application EXT53100024380)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 83.33% allottees for purpose of extension of RERA registration period of the said project.”
  4. 26 March 2025

    Extended at the builder's request (MahaRERA application EXT53100027954)

    Reason the builder gave MahaRERA:
    “We, M/s. Suryapratap Promoters and Builders, hereby declare the following with respect to the project Shree Siddhivinayak Heights bearing registration number. P53100027420 registered under MahaRERA. The delay in the completion of the real e…” Read the full reason“We, M/s. Suryapratap Promoters and Builders, hereby declare the following with respect to the project Shree Siddhivinayak Heights bearing registration number. P53100027420 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 26th March 2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the r…”

Source: SHREE SIDDHIVINAYAK HEIGHTS’s extension records on MahaRERA (P53100027420), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE SIDDHIVINAYAK HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100027420
Status
Completed
Builder
SURYAPRATAP PROMOTERS AND BUILDERS
Location
Vita, Sangli · 415311
Project type
Commercial
Registered on
10 Dec 2020
Completion date at registration
June 2023
Latest completion date
March 2025
Delay so far
21 months
Homes
54
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHREE SIDDHIVINAYAK HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE SIDDHIVINAYAK HEIGHTS3%5%100%70%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE SIDDHIVINAYAK HEIGHTS every month.

SHREE SIDDHIVINAYAK HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE SIDDHIVINAYAK HEIGHTS (7 floors)
  • Land: 1,093 sq m (about 0.3 acres) · sanctioned built-up 1,974 sq m
  • Boundaries filed include: MUNCIPAL ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREE SIDDHIVINAYAK HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE SIDDHIVINAYAK HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE SIDDHIVINAYAK HEIGHTS

What is the possession date of SHREE SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE SIDDHIVINAYAK HEIGHTS in Vita, Sangli is 26 March 2025 — 21 months later than 1 June 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHREE SIDDHIVINAYAK HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE SIDDHIVINAYAK HEIGHTS's builder has filed on MahaRERA, the official one, is 26 March 2025, already 21 months later than the 1 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE SIDDHIVINAYAK HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 May 2024, giving the reason "Respected Sir/Madam, I am writing on behalf of Suryapratap Promoters and Developers, the developer responsible for the construction of the "Siddhivinayak Heights" project located at Vita, Sangli. We would like to bring to your attention the reasons for the delay in completing the construction and request an extension of the completion date until 30th May 2024. The delay in the completion of the project can be attributed to two significant factors, which have severely impacted our construction timeline: 1. Non-availability of CEO, Vita Municipal Council for approving sanctioned plan: Due to…"; to 30 November 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 83.33% allottees for purpose of extension of RERA registration period of the said project."; to 26 March 2025, giving the reason "We, M/s. Suryapratap Promoters and Builders, hereby declare the following with respect to the project Shree Siddhivinayak Heights bearing registration number. P53100027420 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 26th March 2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the r…".

What is the RERA number of SHREE SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE SIDDHIVINAYAK HEIGHTS in Vita, Sangli is P53100027420.

Is SHREE SIDDHIVINAYAK HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS is registered as P53100027420 and its status is "Completed".

What is the construction status of SHREE SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work on SHREE SIDDHIVINAYAK HEIGHTS is 5% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHREE SIDDHIVINAYAK HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHREE SIDDHIVINAYAK HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS is registered on MahaRERA as P53100027420, its MahaRERA status is "Completed", its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE SIDDHIVINAYAK HEIGHTS's possession date changes?

The latest dates are on SHREE SIDDHIVINAYAK HEIGHTS's MahaRERA page (P53100027420). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE SIDDHIVINAYAK HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE SIDDHIVINAYAK HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS has one building filed: SHREE SIDDHIVINAYAK HEIGHTS with 7 floors.

How big is the land of SHREE SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS stands on 1,093 sq m of land (about 0.3 acres), with 1,974 sq m of sanctioned built-up area.

Where can I read reviews of SHREE SIDDHIVINAYAK HEIGHTS?

Google Maps has reviews of SHREE SIDDHIVINAYAK HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE SIDDHIVINAYAK HEIGHTS?

SHREE SIDDHIVINAYAK HEIGHTS by SURYAPRATAP PROMOTERS AND BUILDERS is in Vita, Sangli (pincode 415311), near Vite, Savlaj, Maharashtra, and is registered on MahaRERA as P53100027420, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNCIPAL ROAD.

How many homes are in SHREE SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS has 54 homes in 1 tower registered on MahaRERA.

When was SHREE SIDDHIVINAYAK HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SIDDHIVINAYAK HEIGHTS was registered on MahaRERA on 10 December 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE SIDDHIVINAYAK HEIGHTS?

No court cases are listed for SHREE SIDDHIVINAYAK HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHREE SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SURYAPRATAP PROMOTERS AND BUILDERS.