MALHAR RESIDENCY
by SAYALI DEVELOPERS · Kisan Nagar, Sangli
Possession date of MALHAR RESIDENCY: 31 December 2022, moved from 30 June 2022 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P53100028160. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2022) has passed.
What do you want to know about MALHAR RESIDENCY?
How the possession date of MALHAR RESIDENCY has moved
30 June 2022
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT53100011832)
Reason the builder gave MahaRERA: “DUE TO COVID 1 ST & 2 ND WAVE LABOUR & MATERIAL IS SHORTAGE & SOME CHANGE IS OUR PLANNING.SO OUR WORK IS SLOWLY PROCESS.SO PLEASE GIVE MI EXTENSION FOR UP TO 31.12.2022”
Source: MALHAR RESIDENCY’s extension records on MahaRERA (P53100028160), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MALHAR RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100028160
- Status
- Lapsed (registration period ended)
- Builder
- SAYALI DEVELOPERS
- Location
- Kisan Nagar, Sangli · 415409
- Project type
- Residential / Group Housing
- Registered on
- 10 Feb 2021
- Completion date at registration
- June 2022
- Latest completion date
- December 2022
- Delay so far
- 6 months
- Homes
- 6
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MALHAR RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MALHAR RESIDENCY | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MALHAR RESIDENCY every month.
MALHAR RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: MALHAR RESIDENCY (2 floors)
- Land: 700 sq m (about 0.2 acres) · sanctioned built-up 1 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MALHAR RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MALHAR RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MALHAR RESIDENCY
What is the possession date of MALHAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MALHAR RESIDENCY in Kisan Nagar, Sangli is 31 December 2022 — 6 months later than 30 June 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MALHAR RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MALHAR RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2022, already 6 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MALHAR RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "DUE TO COVID 1 ST & 2 ND WAVE LABOUR & MATERIAL IS SHORTAGE & SOME CHANGE IS OUR PLANNING.SO OUR WORK IS SLOWLY PROCESS.SO PLEASE GIVE MI EXTENSION FOR UP TO 31.12.2022".
What is the RERA number of MALHAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MALHAR RESIDENCY in Kisan Nagar, Sangli is P53100028160.
Is MALHAR RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY is registered as P53100028160 and its status is "Lapsed (registration period ended)".
What is the construction status of MALHAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MALHAR RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MALHAR RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MALHAR RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY is registered on MahaRERA as P53100028160, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MALHAR RESIDENCY's possession date changes?
The latest dates are on MALHAR RESIDENCY's MahaRERA page (P53100028160). GharKundli's Kundli Watch sends a free WhatsApp update on MALHAR RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MALHAR RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY has one building filed: MALHAR RESIDENCY with 2 floors.
How big is the land of MALHAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY stands on 700 sq m of land (about 0.2 acres), with 1 sq m of sanctioned built-up area.
Where can I read reviews of MALHAR RESIDENCY?
Google Maps has reviews of MALHAR RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MALHAR RESIDENCY?
MALHAR RESIDENCY by SAYALI DEVELOPERS is in Kisan Nagar, Sangli (pincode 415409), Maharashtra, and is registered on MahaRERA as P53100028160, per GharKundli's check of MahaRERA records.
How many homes are in MALHAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY has 6 homes in 1 tower registered on MahaRERA.
When was MALHAR RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MALHAR RESIDENCY was registered on MahaRERA on 10 February 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on MALHAR RESIDENCY?
No court cases are listed for MALHAR RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of MALHAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAYALI DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of MALHAR RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Walwa
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.