SHRIRAM COMPLEX
by DURVANK BUILDERS AND DEVELOPERS · Back Side Of Police Line, Sangli
Possession: SHRIRAM COMPLEX is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100029831. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHRIRAM COMPLEX?
How the possession date of SHRIRAM COMPLEX has moved
1 January 2022
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT53100012644)
Reason the builder gave MahaRERA: “Our Project work is slowly progress of due to labour shortage & material shortage. And also some changes of our planning so our project work is slowly progess so please issue the Extension for up to 31.12.2022”
Source: SHRIRAM COMPLEX’s extension records on MahaRERA (P53100029831), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHRIRAM COMPLEX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100029831
- Status
- Completed
- Builder
- DURVANK BUILDERS AND DEVELOPERS
- Location
- Back Side Of Police Line, Sangli · 415409
- Project type
- Others
- Registered on
- 8 Jul 2021
- Completion date at registration
- January 2022
- Latest completion date
- December 2022
- Delay so far
- 11 months
- Homes
- 16
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHRIRAM COMPLEX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHRIRAM COMPLES | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRIRAM COMPLEX every month.
SHRIRAM COMPLEX: buildings, flats and land, as filed on MahaRERA
- Buildings: SHRIRAM COMPLES (6 floors)
- Land: 377 sq m (about 0.1 acres) · sanctioned built-up 469 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHRIRAM COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHRIRAM COMPLEX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHRIRAM COMPLEX
What is the possession date of SHRIRAM COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHRIRAM COMPLEX in Back Side Of Police Line, Sangli is 31 December 2022 — 11 months later than 1 January 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHRIRAM COMPLEX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRIRAM COMPLEX's builder has filed on MahaRERA, the official one, is 31 December 2022, already 11 months later than the 1 January 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHRIRAM COMPLEX extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "Our Project work is slowly progress of due to labour shortage & material shortage. And also some changes of our planning so our project work is slowly progess so please issue the Extension for up to 31.12.2022".
What is the RERA number of SHRIRAM COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHRIRAM COMPLEX in Back Side Of Police Line, Sangli is P53100029831.
Is SHRIRAM COMPLEX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX is registered as P53100029831 and its status is "Completed".
What is the construction status of SHRIRAM COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX's status on MahaRERA is "Completed". As filed by the builder, slab work on SHRIRAM COMPLES is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHRIRAM COMPLEX have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHRIRAM COMPLEX safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX is registered on MahaRERA as P53100029831, its MahaRERA status is "Completed", its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHRIRAM COMPLEX's possession date changes?
The latest dates are on SHRIRAM COMPLEX's MahaRERA page (P53100029831). GharKundli's Kundli Watch sends a free WhatsApp update on SHRIRAM COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHRIRAM COMPLEX have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX has one building filed: SHRIRAM COMPLES with 6 floors.
How big is the land of SHRIRAM COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX stands on 377 sq m of land (about 0.1 acres), with 469 sq m of sanctioned built-up area.
Where can I read reviews of SHRIRAM COMPLEX?
Google Maps has reviews of SHRIRAM COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHRIRAM COMPLEX?
SHRIRAM COMPLEX by DURVANK BUILDERS AND DEVELOPERS is in Back Side Of Police Line, Sangli (pincode 415409), Maharashtra, and is registered on MahaRERA as P53100029831, per GharKundli's check of MahaRERA records.
How many homes are in SHRIRAM COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX has 16 homes in 1 tower registered on MahaRERA.
When was SHRIRAM COMPLEX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRIRAM COMPLEX was registered on MahaRERA on 8 July 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SHRIRAM COMPLEX?
No court cases are listed for SHRIRAM COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHRIRAM COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DURVANK BUILDERS AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SHRIRAM COMPLEX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Walwa
- Devkinandan Residency
- ANANTGANGA HOUSING COMPLEX ANTRGAT KEDARNATH APARTMENT ISLAMPUR
- S A RESIDENCY
- AMAR HEIGHTS
- YUSUFIYA DIAMOND TWIN TOWER
- SAMRUDDHI RESIDENCY
- VIGHANHARTA COMPLEX
- Ishan Row House
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.