Myra Aryam
by MYRA INFRASTRUCTURE · Kalbadevi Road, Mumbai 400002Also near Girgaum, Neral, Grant RoadRegistered on MahaRERA as “Aryam”
What’s in the report? →Possession date of Myra Aryam (MahaRERA P51900052888): 30 April 2028. It has 66 homes (1 BHK and 2 BHK, 322–1091 sq ft carpet), 42% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900052888, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51900052888, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Myra Aryam?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Myra Aryam has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Myra Aryam’s extension records on MahaRERA (P51900052888), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Myra Aryam
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900052888
- Status
- Registered and active
- Builder
- MYRA INFRASTRUCTURE
- Location
- Kalbadevi Road, Mumbai · 400002
- Project type
- Others
- Registered on
- 5 Oct 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 66
- Sold or booked
- 42%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Myra Aryam, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aryam | 100% | 100% | 95% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- Aryam: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Myra Aryam every 1–2 months.
Myra Aryam: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 482 – 1,091 | 56 |
| 1 BHK | 322 – 482 | 10 |
| Other | 173 – 851 | 9 |
- Buildings: Aryam (21 floors, 75 units)
- Land: 532 sq m (about 0.1 acres) · sanctioned built-up 3,944 sq m · recreational space 134 sq m
- Land, as filed: 969
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Myra Aryam →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Myra Aryam: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Myra Aryam
What is the possession date of Myra Aryam?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Myra Aryam in Kalbadevi Road, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Myra Aryam?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Myra Aryam's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Myra Aryam?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Myra Aryam in Kalbadevi Road, Mumbai is P51900052888.
Is Myra Aryam registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam is registered as P51900052888 and its status is "Registered and active".
What is the current construction status of Myra Aryam? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Aryam is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Myra Aryam have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Myra Aryam safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam is registered on MahaRERA as P51900052888, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Myra Aryam?
Myra Aryam is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Myra Aryam are 322 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Myra Aryam?
For a flat in Myra Aryam (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Myra Aryam received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Myra Aryam a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam is a redevelopment: 37 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Myra Aryam uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Myra Aryam was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Myra Aryam's possession date changes?
The latest dates are on Myra Aryam's MahaRERA page (P51900052888). GharKundli's Kundli Watch sends a free WhatsApp update on Myra Aryam every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Myra Aryam have?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam has one building filed: Aryam with 21 floors and 75 units.
What are the flat sizes (carpet area) in Myra Aryam?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Myra Aryam: 2 BHK: 482 to 1091 sq ft carpet (56 homes); 1 BHK: 322 to 482 sq ft carpet (10 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Myra Aryam?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam stands on 532 sq m of land (about 0.1 acres), with 3,944 sq m of sanctioned built-up area and 134 sq m of recreational open space.
What are the reviews of Myra Aryam?
Google Maps has reviews of Myra Aryam written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Myra Aryam?
Myra Aryam by MYRA INFRASTRUCTURE is in Kalbadevi Road, Mumbai, pincode 400002 (near Girgaum, Neral, Grant Road), Maharashtra, and is registered on MahaRERA as P51900052888, per GharKundli's check of MahaRERA records. Its land is filed as 969. GharKundli lists all 32 MahaRERA projects in Kalbadevi (400002).
How many flats are in Myra Aryam, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam has 66 homes in 1 tower registered on MahaRERA, and 42% of them are sold or booked.
When was Myra Aryam registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Myra Aryam was registered on MahaRERA on 5 October 2023. GharKundli did not find a title report on the land on file there.
Does Myra Aryam have any legal issues or court cases?
No court cases are listed for Myra Aryam on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Myra Aryam?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MYRA INFRASTRUCTURE.
Check it yourself on MahaRERA
- How to check the possession date of Myra Aryam
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai City →
Other projects in Kalbadevi (400002)
- One Marina
- Ocean Drive
- Coastal Heights
- Krishvi Escape
- Subodh Sagar
- Prestige Ocean Towers - North
- Prestige Ocean Towers - South
- La Belleza
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.