Lodha Matunga Signet
by Lodha Developers Limited · Matunga, Mumbai 400022Registered on MahaRERA as “Matunga Signet”
What’s in the report? →Possession date of Lodha Matunga Signet (MahaRERA P51900077196): 30 January 2030. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900077196, and currently active. Its completion date is now January 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51900077196, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Lodha Matunga Signet?
3 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Lodha Matunga Signet has moved
30 September 2029
Completion date given when the project was registered
30 January 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Lodha Matunga Signet’s extension records on MahaRERA (P51900077196), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lodha Matunga Signet
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the January 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900077196
- Status
- Registered and active
- Builder
- Lodha Developers Limited
- Location
- Matunga, Mumbai · 400022
- Project type
- Commercial
- Registered on
- 29 Jul 2024
- Completion date at registration
- September 2029
- Latest completion date
- January 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 180
Construction progress of Lodha Matunga Signet, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No -7 | 30% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building No -7: covers Plinth
Latest CC order on MahaRERA: dated 11/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Matunga Signet every 1–2 months.
Lodha Matunga Signet: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 300 – 4,162 | 219 |
| Other | 300 – 1,400 | 48 |
- Buildings: Building No -7 (26 floors, 267 units)
- Land: 3,720 sq m (about 0.9 acres) · sanctioned built-up 9,056 sq m · recreational space 372 sq m
- Land, as filed: C.S.No.6 Part,7 Part,41 Part
- Map: Get directions
The builder’s record and reviews
Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects.
Read Google reviews of Lodha Matunga Signet →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lodha Matunga Signet: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Lodha Matunga Signet
What is the possession date of Lodha Matunga Signet?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Matunga Signet in Matunga, Mumbai is 30 January 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Lodha Matunga Signet?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Matunga Signet's builder has filed on MahaRERA, the official one, is 30 January 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Lodha Matunga Signet?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Matunga Signet in Matunga, Mumbai is P51900077196.
Is Lodha Matunga Signet registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet is registered as P51900077196 and its status is "Registered and active".
What is the current construction status of Lodha Matunga Signet? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No -7 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Lodha Matunga Signet have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Lodha Matunga Signet safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet is registered on MahaRERA as P51900077196, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Lodha Matunga Signet?
Lodha Matunga Signet is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Lodha Matunga Signet?
For a flat in Lodha Matunga Signet (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Lodha Matunga Signet received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet is still under construction, with 30 January 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Lodha Matunga Signet uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lodha Matunga Signet was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Lodha Matunga Signet's possession date changes?
The latest dates are on Lodha Matunga Signet's MahaRERA page (P51900077196). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Matunga Signet every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lodha Matunga Signet have?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet has one building filed: Building No -7 with 26 floors and 267 units.
How big is the land of Lodha Matunga Signet?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet stands on 3,720 sq m of land (about 0.9 acres), with 9,056 sq m of sanctioned built-up area and 372 sq m of recreational open space.
What is the track record of Lodha Matunga Signet's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Lodha Matunga Signet?
Google Maps has reviews of Lodha Matunga Signet written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Lodha Matunga Signet?
Lodha Matunga Signet by Lodha Developers Limited is in Matunga, Mumbai, pincode 400022, Maharashtra, and is registered on MahaRERA as P51900077196, per GharKundli's check of MahaRERA records. Its land is filed as C.S.No.6 Part,7 Part,41 Part. GharKundli lists all 98 MahaRERA projects in Sion (400022).
How many flats are in Lodha Matunga Signet, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet has 0 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was Lodha Matunga Signet registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Matunga Signet was registered on MahaRERA on 29 July 2024. GharKundli did not find a title report on the land on file there.
Does Lodha Matunga Signet have any legal issues or court cases?
3 court cases are listed for Lodha Matunga Signet on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Lodha Matunga Signet?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Lodha Matunga Signet
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai City →
Other projects in Sion (400022)
All 98 projects in Sion (400022) →Other projects by Lodha Developers Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.