PUSHPAM APPARTMENT

by JAGTAP PAWAR ASSOCIATES · Sarabazar, SataraAlso near Karanje Tarf

Possession date of PUSHPAM APPARTMENT: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700032432, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about PUSHPAM APPARTMENT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PUSHPAM APPARTMENT has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PUSHPAM APPARTMENT’s extension records on MahaRERA (P52700032432), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PUSHPAM APPARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700032432
Status
Registered and active
Builder
JAGTAP PAWAR ASSOCIATES
Location
Sarabazar, Satara · 415001
Project type
Residential / Group Housing
Registered on
4 Jan 2022
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
38
Sold or booked
51%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of PUSHPAM APPARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PUSHPAM APPARTMENT100%70%90%90%

Commencement certificate (CC), as filed on MahaRERA

  • PUSHPAM APPARTMENT: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PUSHPAM APPARTMENT every month.

PUSHPAM APPARTMENT: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PUSHPAM APPARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PUSHPAM APPARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PUSHPAM APPARTMENT

What is the possession date of PUSHPAM APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PUSHPAM APPARTMENT in Sarabazar, Satara is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PUSHPAM APPARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PUSHPAM APPARTMENT's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of PUSHPAM APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PUSHPAM APPARTMENT in Sarabazar, Satara is P52700032432.

Is PUSHPAM APPARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHPAM APPARTMENT is registered as P52700032432 and its status is "Registered and active".

What is the construction status of PUSHPAM APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHPAM APPARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PUSHPAM APPARTMENT is 70% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does PUSHPAM APPARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is PUSHPAM APPARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHPAM APPARTMENT is registered on MahaRERA as P52700032432, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PUSHPAM APPARTMENT's possession date changes?

The latest dates are on PUSHPAM APPARTMENT's MahaRERA page (P52700032432). GharKundli's Kundli Watch sends a free WhatsApp update on PUSHPAM APPARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PUSHPAM APPARTMENT have?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHPAM APPARTMENT has one building filed: PUSHPAM APPARTMENT with 12 floors and 47 units.

How big is the land of PUSHPAM APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHPAM APPARTMENT stands on 1,590 sq m of land (about 0.4 acres), with 4,801 sq m of sanctioned built-up area.

Where can I read reviews of PUSHPAM APPARTMENT?

Google Maps has reviews of PUSHPAM APPARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PUSHPAM APPARTMENT?

PUSHPAM APPARTMENT by JAGTAP PAWAR ASSOCIATES is in Sarabazar, Satara (pincode 415001), near Karanje Tarf, Maharashtra, and is registered on MahaRERA as P52700032432, per GharKundli's check of MahaRERA records.

How many homes are in PUSHPAM APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHPAM APPARTMENT has 38 homes in 1 tower registered on MahaRERA, and 51% of them are sold or booked.

When was PUSHPAM APPARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHPAM APPARTMENT was registered on MahaRERA on 4 January 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on PUSHPAM APPARTMENT?

No court cases are listed for PUSHPAM APPARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PUSHPAM APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JAGTAP PAWAR ASSOCIATES.

Other projects in Satara

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.