CHAITANYA PRABHU
by SHREE CHAITANYA BUILDERS · Ramacha Got, SataraAlso near Mangalwar Peth, Parali
Possession date of CHAITANYA PRABHU: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52700046762, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about CHAITANYA PRABHU?
How the possession date of CHAITANYA PRABHU has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: CHAITANYA PRABHU’s extension records on MahaRERA (P52700046762), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CHAITANYA PRABHU
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52700046762
- Status
- Registered and active
- Builder
- SHREE CHAITANYA BUILDERS
- Location
- Ramacha Got, Satara · 415001
- Project type
- Residential / Group Housing
- Registered on
- 5 Sep 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of CHAITANYA PRABHU, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CHAITANYA PRABHU | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CHAITANYA PRABHU every month.
CHAITANYA PRABHU: buildings, flats and land, as filed on MahaRERA
- Buildings: CHAITANYA PRABHU (7 floors)
- Land: 402 sq m (about 0.1 acres) · sanctioned built-up 1,300 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of CHAITANYA PRABHU →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CHAITANYA PRABHU: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CHAITANYA PRABHU
What is the possession date of CHAITANYA PRABHU?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CHAITANYA PRABHU in Ramacha Got, Satara is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for CHAITANYA PRABHU?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CHAITANYA PRABHU's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of CHAITANYA PRABHU?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CHAITANYA PRABHU in Ramacha Got, Satara is P52700046762.
Is CHAITANYA PRABHU registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CHAITANYA PRABHU is registered as P52700046762 and its status is "Registered and active".
What is the construction status of CHAITANYA PRABHU?
According to GharKundli's check of MahaRERA records (updated November 2026), CHAITANYA PRABHU's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CHAITANYA PRABHU is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does CHAITANYA PRABHU have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is CHAITANYA PRABHU safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), CHAITANYA PRABHU is registered on MahaRERA as P52700046762, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CHAITANYA PRABHU's possession date changes?
The latest dates are on CHAITANYA PRABHU's MahaRERA page (P52700046762). GharKundli's Kundli Watch sends a free WhatsApp update on CHAITANYA PRABHU every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CHAITANYA PRABHU have?
According to GharKundli's check of MahaRERA records (updated November 2026), CHAITANYA PRABHU has one building filed: CHAITANYA PRABHU with 7 floors.
How big is the land of CHAITANYA PRABHU?
According to GharKundli's check of MahaRERA records (updated November 2026), CHAITANYA PRABHU stands on 402 sq m of land (about 0.1 acres), with 1,300 sq m of sanctioned built-up area.
Where can I read reviews of CHAITANYA PRABHU?
Google Maps has reviews of CHAITANYA PRABHU written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CHAITANYA PRABHU?
CHAITANYA PRABHU by SHREE CHAITANYA BUILDERS is in Ramacha Got, Satara (pincode 415001), near Mangalwar Peth, Parali, Maharashtra, and is registered on MahaRERA as P52700046762, per GharKundli's check of MahaRERA records.
How many homes are in CHAITANYA PRABHU?
According to GharKundli's check of MahaRERA records (updated November 2026), CHAITANYA PRABHU has 14 homes in 1 tower registered on MahaRERA.
When was CHAITANYA PRABHU registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CHAITANYA PRABHU was registered on MahaRERA on 5 September 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on CHAITANYA PRABHU?
No court cases are listed for CHAITANYA PRABHU on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of CHAITANYA PRABHU?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE CHAITANYA BUILDERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CHAITANYA PRABHU
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Satara
Other projects by SHREE CHAITANYA BUILDERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.