Eakadanta Sankul Phase- III
by EAKADANTA REALTORS · Dadar West, RaigarhAlso near Panvel, Powai, Prabhu Ali
Possession date of Eakadanta Sankul Phase- III: 30 October 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed.
Registered on MahaRERA under P52000004372. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (October 2026) has passed.
GharKundli’s full report on Eakadanta Sankul Phase- III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Eakadanta Sankul Phase-IP52000005394 · possession 30 Dec 2020
- Eakadanta Sankul Phase-IIP52000004401 · possession 30 Oct 2026
- MahaRERA registration
- P52000004372
- Status
- Lapsed (registration period ended)
- Builder
- EAKADANTA REALTORS
- Location
- Dadar West, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- June 2026
- Latest completion date
- October 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 96
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Eakadanta Sankul Phase- III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bldg No 10 | 0% | 0% | 0% | 0% |
| Bldg No 11 | 0% | 0% | 0% | 0% |
| Bldg No 5 | 0% | 0% | 0% | 0% |
| Bldg No 6 | 0% | 0% | 0% | 0% |
| Bldg No 7 | 0% | 0% | 0% | 0% |
| Bldg No 8 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Eakadanta Sankul Phase- III every month.
Eakadanta Sankul Phase- III: buildings, flats and land, as filed on MahaRERA
- Buildings: Bldg No 10 (6 floors) · Bldg No 11 (6 floors) · Bldg No 5 (6 floors) · Bldg No 6 (6 floors) · Bldg No 7 (6 floors) · Bldg No 8 (6 floors)
- Land: 11,280 sq m (about 2.8 acres) · sanctioned built-up 10,828 sq m · recreational space 1,082 sq m
- Map: the location the builder filed on MahaRERA
Kundli Watch
Eakadanta Sankul Phase- III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Eakadanta Sankul Phase- III
What is the possession date of Eakadanta Sankul Phase- III?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Eakadanta Sankul Phase- III in Dadar West, Raigarh is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Eakadanta Sankul Phase- III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Eakadanta Sankul Phase- III's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Eakadanta Sankul Phase- III?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Eakadanta Sankul Phase- III in Dadar West, Raigarh is P52000004372.
Is Eakadanta Sankul Phase- III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Eakadanta Sankul Phase- III is registered as P52000004372 and its status is "Lapsed (registration period ended)".
What is the construction status of Eakadanta Sankul Phase- III?
According to GharKundli's check of MahaRERA records (updated November 2026), Eakadanta Sankul Phase- III's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 0% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does Eakadanta Sankul Phase- III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Eakadanta Sankul Phase- III safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Eakadanta Sankul Phase- III is registered on MahaRERA as P52000004372, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Eakadanta Sankul Phase- III have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Eakadanta Sankul Phase-I (P52000005394, possession 30 Dec 2020); Eakadanta Sankul Phase-II (P52000004401, possession 30 Oct 2026). Check that your agreement names the registration of your own wing.
How can I get updates if Eakadanta Sankul Phase- III's possession date changes?
The latest dates are on Eakadanta Sankul Phase- III's MahaRERA page (P52000004372). GharKundli's Kundli Watch sends a free WhatsApp update on Eakadanta Sankul Phase- III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Eakadanta Sankul Phase- III have?
According to GharKundli's check of MahaRERA records (updated November 2026), Eakadanta Sankul Phase- III has 6 buildings filed: Bldg No 10 with 6 floors; Bldg No 11 with 6 floors; Bldg No 5 with 6 floors; Bldg No 6 with 6 floors; Bldg No 7 with 6 floors; Bldg No 8 with 6 floors.
How big is the land of Eakadanta Sankul Phase- III?
According to GharKundli's check of MahaRERA records (updated November 2026), Eakadanta Sankul Phase- III stands on 11,280 sq m of land (about 2.8 acres), with 10,828 sq m of sanctioned built-up area and 1,082 sq m of recreational open space.
Where is Eakadanta Sankul Phase- III?
Eakadanta Sankul Phase- III by EAKADANTA REALTORS is in Dadar West, Raigarh (pincode 410206), near Panvel, Powai, Prabhu Ali, Maharashtra, and is registered on MahaRERA as P52000004372, per GharKundli's check of MahaRERA records.
How many homes are in Eakadanta Sankul Phase- III?
According to GharKundli's check of MahaRERA records (updated November 2026), Eakadanta Sankul Phase- III has 96 homes in 6 towers registered on MahaRERA.
When was Eakadanta Sankul Phase- III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Eakadanta Sankul Phase- III was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Eakadanta Sankul Phase- III?
No court cases are listed for Eakadanta Sankul Phase- III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Eakadanta Sankul Phase- III?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is EAKADANTA REALTORS, which has 2 other projects registered on MahaRERA.
All projects with possession due in 2026 in Raigad →
All projects in Panvel (410206) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.