Possession date of Eakadanta Sankul Phase-II: 30 October 2026, moved from 30 June 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000004401, and currently active. Its completion date has moved from June 2023 to October 2026: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Eakadanta Sankul Phase-II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Eakadanta Sankul Phase-II has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT52000016933)

    Reason the builder gave MahaRERA:
    “The project is under construction & we have completed majority of the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the pro…” Read the full reason“The project is under construction & we have completed majority of the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed.”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT52000024192)

    Reason the builder gave MahaRERA:
    “The project is under construction & we have completed majority of work on the project. However due to some unavoidable circumstances like imposition of lockdown and consequently migration of labour and contractors we are facing difficulty i…” Read the full reason“The project is under construction & we have completed majority of work on the project. However due to some unavoidable circumstances like imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time and also issue of Non availability Electricity from Electricity Department. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the above circumstances it is getting delayed.”
  4. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Eakadanta Sankul Phase-II’s extension records on MahaRERA (P52000004401), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Eakadanta Sankul Phase-II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000004401
Status
Registered and active
Builder
EAKADANTA REALTORS
Location
Dadar West, Raigarh · 410206
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
June 2023
Latest completion date
October 2026
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
98
Towers
6
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Eakadanta Sankul Phase-II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Bldg No 9100%100%100%80%
Bldg No 10%100%0%0%
Bldg No 2100%100%0%0%
Bldg No 3100%100%100%100%
Bldg No 4100%100%100%100%
Bldg No 17100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Eakadanta Sankul Phase-II every month.

Eakadanta Sankul Phase-II: buildings, flats and land, as filed on MahaRERA

  • Buildings: Bldg No 9 (6 floors) · Bldg No 1 (6 floors) · Bldg No 2 (6 floors) · Bldg No 3 (6 floors) · Bldg No 4 (6 floors) · Bldg No 17 (6 floors)
  • Land: 11,280 sq m (about 2.8 acres) · sanctioned built-up 10,828 sq m · recreational space 1,082 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Eakadanta Realtors has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 24 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Eakadanta Sankul Phase-II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Eakadanta Sankul Phase-II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Eakadanta Sankul Phase-II

What is the possession date of Eakadanta Sankul Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Eakadanta Sankul Phase-II in Dadar West, Raigarh is 30 October 2026 — 36 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Eakadanta Sankul Phase-II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Eakadanta Sankul Phase-II's builder has filed on MahaRERA, the official one, is 30 October 2026, already 36 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Eakadanta Sankul Phase-II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2024, giving the reason "The project is under construction & we have completed majority of the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed."; to 30 June 2026, giving the reason "The project is under construction & we have completed majority of work on the project. However due to some unavoidable circumstances like imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time and also issue of Non availability Electricity from Electricity Department. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the above circumstances it is getting delayed.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Eakadanta Sankul Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Eakadanta Sankul Phase-II in Dadar West, Raigarh is P52000004401.

Is Eakadanta Sankul Phase-II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II is registered as P52000004401 and its status is "Registered and active".

What is the construction status of Eakadanta Sankul Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 6 towers. GharKundli's full report compares construction progress with the deadline.

Does Eakadanta Sankul Phase-II have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Eakadanta Sankul Phase-II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II is registered on MahaRERA as P52000004401, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Eakadanta Sankul Phase-II have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Eakadanta Sankul Phase-I (P52000005394, possession 30 Dec 2020); Eakadanta Sankul Phase- III (P52000004372, possession 30 Oct 2026). Check that your agreement names the registration of your own wing.

How can I get updates if Eakadanta Sankul Phase-II's possession date changes?

The latest dates are on Eakadanta Sankul Phase-II's MahaRERA page (P52000004401). GharKundli's Kundli Watch sends a free WhatsApp update on Eakadanta Sankul Phase-II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Eakadanta Sankul Phase-II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II has 6 buildings filed: Bldg No 9 with 6 floors; Bldg No 1 with 6 floors; Bldg No 2 with 6 floors; Bldg No 3 with 6 floors; Bldg No 4 with 6 floors; Bldg No 17 with 6 floors.

How big is the land of Eakadanta Sankul Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II stands on 11,280 sq m of land (about 2.8 acres), with 10,828 sq m of sanctioned built-up area and 1,082 sq m of recreational open space.

What is the track record of Eakadanta Sankul Phase-II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Realtors has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 24 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Eakadanta Sankul Phase-II?

Google Maps has reviews of Eakadanta Sankul Phase-II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Eakadanta Sankul Phase-II?

Eakadanta Sankul Phase-II by EAKADANTA REALTORS is in Dadar West, Raigarh (pincode 410206), near Panvel, Powai, Karanjade, Maharashtra, and is registered on MahaRERA as P52000004401, per GharKundli's check of MahaRERA records.

How many homes are in Eakadanta Sankul Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II has 98 homes in 6 towers registered on MahaRERA.

When was Eakadanta Sankul Phase-II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Eakadanta Sankul Phase-II was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Eakadanta Sankul Phase-II?

No court cases are listed for Eakadanta Sankul Phase-II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Eakadanta Sankul Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EAKADANTA REALTORS, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Raigad →

Other projects in Dadar West

All 2,664 projects in Panvel (410206) →

Other projects by EAKADANTA REALTORS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.