Chintamani Aryavrat Project

by M/S Chintamani Land and Housing LLP · Dadar West, Mumbai 400028Also near Bhawani Shankar, Prabhadevi, MatungaRegistered on MahaRERA as “ARYAVRAT PROJECT”

What’s in the report? →

Possession date of Chintamani Aryavrat Project (MahaRERA P51900024338): 30 June 2028, moved from 30 December 2023 (54 months later). It has 87 homes (1 BHK, 2 BHK and 3 BHK, 218–1592 sq ft carpet), 66% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900024338, and currently active.

Source: MahaRERA website — records for P51900024338, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Chintamani Aryavrat Project?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Chintamani Aryavrat Project has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51900018504)

    Reason the builder gave MahaRERA:
    “CONSTRUCTION UPDATE, EXPLANATORY NOTE FOR DELAY AND REASON FOR EXTENSION OF THE ARYAVRAT PROJECT REREA REGISTRATION NO. P51900024338 • We are seeking RERA Extension of the project till 31st December 2024. • Project Comprises of Wing A-Major…” Read the full reason“CONSTRUCTION UPDATE, EXPLANATORY NOTE FOR DELAY AND REASON FOR EXTENSION OF THE ARYAVRAT PROJECT REREA REGISTRATION NO. P51900024338 • We are seeking RERA Extension of the project till 31st December 2024. • Project Comprises of Wing A-Majorly of Sale Component & B Wing-Majorly Rehab Component. • We have received Amended IOD of the Project on 23/06/2023 and CC upto 15th Floors of A wing and upto Top of 21st Floor of Wing B, dated 30.12.2021. • We have obtained more than 100% % consent of flat buyers. In Project B wing (Sale) we have sold Only One flat as on date. Remaining sale area is in th…”
  3. 30 June 2028

    Extended at the builder's request (MahaRERA application EA20072621809)

    Reason the builder gave MahaRERA:
    “• We are seeking RERA Extension of the project till 30th June 2028. • Project Comprises of Wing A-Majorly of Sale Component & B Wing-Majorly Rehab Component. • We have received Amended IOD of Gr. Flr + 16 Upper Floors of the Project on 23/0…” Read the full reason“• We are seeking RERA Extension of the project till 30th June 2028. • Project Comprises of Wing A-Majorly of Sale Component & B Wing-Majorly Rehab Component. • We have received Amended IOD of Gr. Flr + 16 Upper Floors of the Project on 23/06/2023 and CC upto 12th Floors (Part) of A wing and upto Top of 22nd Floor of Wing B, dated 01.02.24. • We have received Part OC for the entire B wing (Technically it is Full OC for B Wing and Part OC of entire project comprises of wing A & B) on 20th December 2024 and Possession of the flat is already given. The flat owners have formed Association of Per…”

Source: Chintamani Aryavrat Project’s extension records on MahaRERA (P51900024338), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Chintamani Aryavrat Project

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the June 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900024338
Status
Registered and active
Builder
M/S Chintamani Land and Housing LLP
Location
Dadar West, Mumbai · 400028
Project type
Residential / Group Housing
Registered on
5 Feb 2020
Completion date at registration
December 2023
Latest completion date
June 2028
Delay so far
54 months
Homes
87
Sold or booked
66%
Towers
2
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Chintamani Aryavrat Project, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing B100%100%100%0%
Wing A100%72%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing B: covers 24 floors
  • Wing A: covers 12 Habitable Floor Part

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Chintamani Aryavrat Project every 1–2 months.

Chintamani Aryavrat Project: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK452 – 92941
3 BHK1,169 – 1,17819
1 BHK218 – 50218
4 BHK1,5929
  • Buildings: Wing B (24 floors, 57 units) · Wing A (17 floors, 30 units)
  • Land: 3,146 sq m (about 0.8 acres) · recreational space 256 sq m
  • Boundaries filed include: SK BOLE ROAD
  • Land, as filed: FP NO 240 TPS IV MAHIM DIVISION
  • Map: Get directions

The builder’s record and reviews

Triumph Ventures (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects.

Read Google reviews of Chintamani Aryavrat Project →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Chintamani Aryavrat Project: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Chintamani Aryavrat Project

What is the possession date of Chintamani Aryavrat Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Chintamani Aryavrat Project in Dadar West, Mumbai is 30 June 2028 — 54 months later than 30 December 2023, the date given at registration.

The date has already moved 54 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Chintamani Aryavrat Project?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Chintamani Aryavrat Project's builder has filed on MahaRERA, the official one, is 30 June 2028, already 54 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Chintamani Aryavrat Project extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "CONSTRUCTION UPDATE, EXPLANATORY NOTE FOR DELAY AND REASON FOR EXTENSION OF THE ARYAVRAT PROJECT REREA REGISTRATION NO. P51900024338 • We are seeking RERA Extension of the project till 31st December 2024. • Project Comprises of Wing A-Majorly of Sale Component & B Wing-Majorly Rehab Component. • We have received Amended IOD of the Project on 23/06/2023 and CC upto 15th Floors of A wing and upto Top of 21st Floor of Wing B, dated 30.12.2021. • We have obtained more than 100% % consent of flat buyers. In Project B wing (Sale) we have sold Only One flat as on date. Remaining sale area is in th…"; to 30 June 2028, giving the reason "• We are seeking RERA Extension of the project till 30th June 2028. • Project Comprises of Wing A-Majorly of Sale Component & B Wing-Majorly Rehab Component. • We have received Amended IOD of Gr. Flr + 16 Upper Floors of the Project on 23/06/2023 and CC upto 12th Floors (Part) of A wing and upto Top of 22nd Floor of Wing B, dated 01.02.24. • We have received Part OC for the entire B wing (Technically it is Full OC for B Wing and Part OC of entire project comprises of wing A & B) on 20th December 2024 and Possession of the flat is already given. The flat owners have formed Association of Per…".

What is the RERA number of Chintamani Aryavrat Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Chintamani Aryavrat Project in Dadar West, Mumbai is P51900024338.

Is Chintamani Aryavrat Project registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project is registered as P51900024338 and its status is "Registered and active".

What is the current construction status of Chintamani Aryavrat Project? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 72% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Chintamani Aryavrat Project have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Chintamani Aryavrat Project safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project is registered on MahaRERA as P51900024338, its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Chintamani Aryavrat Project?

Chintamani Aryavrat Project is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Chintamani Aryavrat Project are 218 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Chintamani Aryavrat Project?

For a flat in Chintamani Aryavrat Project (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Chintamani Aryavrat Project received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project is still under construction, with 30 June 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Chintamani Aryavrat Project uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Chintamani Aryavrat Project was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Chintamani Aryavrat Project's possession date changes?

The latest dates are on Chintamani Aryavrat Project's MahaRERA page (P51900024338). GharKundli's Kundli Watch sends a free WhatsApp update on Chintamani Aryavrat Project every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Chintamani Aryavrat Project have?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project has 2 buildings filed: Wing B with 24 floors and 57 units; Wing A with 17 floors and 30 units.

What are the flat sizes (carpet area) in Chintamani Aryavrat Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Chintamani Aryavrat Project: 2 BHK: 452 to 929 sq ft carpet (41 homes); 3 BHK: 1169 to 1178 sq ft carpet (19 homes); 1 BHK: 218 to 502 sq ft carpet (18 homes); 4 BHK: 1592 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Chintamani Aryavrat Project?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project stands on 3,146 sq m of land (about 0.8 acres) and 256 sq m of recreational open space.

What is the track record of Chintamani Aryavrat Project's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Triumph Ventures (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Chintamani Aryavrat Project?

Google Maps has reviews of Chintamani Aryavrat Project written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Chintamani Aryavrat Project?

Chintamani Aryavrat Project by M/S Chintamani Land and Housing LLP is in Dadar West, Mumbai, pincode 400028 (near Bhawani Shankar, Prabhadevi, Matunga), Maharashtra, and is registered on MahaRERA as P51900024338, per GharKundli's check of MahaRERA records. Its boundaries filed there include SK BOLE ROAD. Its land is filed as FP NO 240 TPS IV MAHIM DIVISION. GharKundli lists all 148 MahaRERA projects in Dadar West (400028).

How many flats are in Chintamani Aryavrat Project, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project has 87 homes in 2 towers registered on MahaRERA, and 66% of them are sold or booked.

When was Chintamani Aryavrat Project registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Chintamani Aryavrat Project was registered on MahaRERA on 5 February 2020. GharKundli did not find a title report on the land on file there.

Does Chintamani Aryavrat Project have any legal issues or court cases?

1 court case is listed for Chintamani Aryavrat Project on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Chintamani Aryavrat Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S Chintamani Land and Housing LLP.

All projects with possession due in 2028 in Mumbai City →

Other projects in Dadar West (400028)

All 148 projects in Dadar West (400028) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.