SHREE SAI ARTI

by V.K DEVELOPERS · Dadar West, Mumbai

Registered on MahaRERA under P51900048871, and currently active. Its completion date has moved from December 2025 to December 2026, 12 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
P51900048871
Status
Registered and active
Builder
V.K DEVELOPERS
Location
Dadar West, Mumbai · 400028
Project type
Residential / Group Housing
Registered on
24 Jan 2023
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
23
Sold or booked
26%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

GharKundli’s full report on SHREE SAI ARTI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

SHREE SAI ARTI: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SHREE SAI ARTI

Is SHREE SAI ARTI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SAI ARTI is registered as P51900048871 and its status is "Registered and active".

Where is SHREE SAI ARTI?

SHREE SAI ARTI by V.K DEVELOPERS is in Dadar West, Mumbai (pincode 400028), Maharashtra, and is registered on MahaRERA as P51900048871, per GharKundli's check of MahaRERA records.

When is possession of SHREE SAI ARTI due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE SAI ARTI in Dadar West, Mumbai is 30 December 2026 — 12 months later than 30 December 2025, the date given at registration.

Does SHREE SAI ARTI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SHREE SAI ARTI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V.K DEVELOPERS.

Other projects in pincode 400028

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.