Skip to content
GharKundli

YASH TRINITY

by Bhalchandra Vinayak Wadnerkar · Dadar West, Mumbai

Possession date of YASH TRINITY: 30 January 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900025356, and currently active. Its completion date is now January 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about YASH TRINITY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of YASH TRINITY has moved

  1. 30 September 2026

    Completion date given when the project was registered

  2. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: YASH TRINITY’s extension records on MahaRERA (P51900025356), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on YASH TRINITY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900025356
Status
Registered and active
Builder
Bhalchandra Vinayak Wadnerkar
Location
Dadar West, Mumbai · 400028
Project type
Others
Registered on
30 Apr 2020
Completion date at registration
September 2026
Latest completion date
January 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
49
Sold or booked
66%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of YASH TRINITY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
YASH TRINITY100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • YASH TRINITY: covers 22 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on YASH TRINITY every month.

YASH TRINITY: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK399 – 43838
Office Space150 – 1,02417
Shops30 – 47411
2 BHK560 – 58711
  • Buildings: YASH TRINITY (22 floors, 77 units)
  • Car parking: 30 covered
  • Land: 430 sq m (about 0.1 acres) · sanctioned built-up 3,204 sq m

The builder’s record and reviews

Bhalchandra Vinayak Wadnerkar has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 102 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of YASH TRINITY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

YASH TRINITY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about YASH TRINITY

What is the possession date of YASH TRINITY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for YASH TRINITY in Dadar West, Mumbai is 30 January 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for YASH TRINITY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date YASH TRINITY's builder has filed on MahaRERA, the official one, is 30 January 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of YASH TRINITY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of YASH TRINITY in Dadar West, Mumbai is P51900025356.

Is YASH TRINITY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), YASH TRINITY is registered as P51900025356 and its status is "Registered and active".

What is the construction status of YASH TRINITY?

According to GharKundli's check of MahaRERA records (updated October 2026), YASH TRINITY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on YASH TRINITY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does YASH TRINITY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is YASH TRINITY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), YASH TRINITY is registered on MahaRERA as P51900025356, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if YASH TRINITY's possession date changes?

The latest dates are on YASH TRINITY's MahaRERA page (P51900025356). GharKundli's Kundli Watch sends a free WhatsApp update on YASH TRINITY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does YASH TRINITY have?

According to GharKundli's check of MahaRERA records (updated October 2026), YASH TRINITY has one building filed: YASH TRINITY with 22 floors and 77 units.

What are the flat sizes (carpet area) in YASH TRINITY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for YASH TRINITY: 1 BHK: 399 to 438 sq ft carpet (38 homes); 2 BHK: 560 to 587 sq ft carpet (11 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does YASH TRINITY have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 30 covered car parking spaces for YASH TRINITY.

How big is the land of YASH TRINITY?

According to GharKundli's check of MahaRERA records (updated October 2026), YASH TRINITY stands on 430 sq m of land (about 0.1 acres), with 3,204 sq m of sanctioned built-up area.

What is the track record of YASH TRINITY's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhalchandra Vinayak Wadnerkar has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 102 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of YASH TRINITY?

Google Maps has reviews of YASH TRINITY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is YASH TRINITY?

YASH TRINITY by Bhalchandra Vinayak Wadnerkar is in Dadar West, Mumbai (pincode 400028), Maharashtra, and is registered on MahaRERA as P51900025356, per GharKundli's check of MahaRERA records.

How many homes are in YASH TRINITY?

According to GharKundli's check of MahaRERA records (updated October 2026), YASH TRINITY has 49 homes in 1 tower registered on MahaRERA, and 66% of them are sold or booked.

When was YASH TRINITY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), YASH TRINITY was registered on MahaRERA on 30 April 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on YASH TRINITY?

No court cases are listed for YASH TRINITY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of YASH TRINITY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Bhalchandra Vinayak Wadnerkar, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai City →

Other projects in Dadar West

All 148 projects in Dadar West (400028) →

Other projects by Bhalchandra Vinayak Wadnerkar

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.