DATTATIRTH

by GAJRAJ BUILDERS · Kothrud, KolhapurAlso near Narsobawadi

Possession date of DATTATIRTH: 28 August 2024, moved from 31 July 2018 (73 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100003610. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (August 2024) has passed.

What do you want to know about DATTATIRTH?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DATTATIRTH has moved

  1. 31 July 2018

    Completion date given when the project was registered

  2. 27 December 2021

    Extended at the builder's request (MahaRERA application EXT53000008705)

    Reason the builder gave MahaRERA:
    “Obtained occupancy certificate(Partial) on 15/05/2019. Due to heavy rain in Kolhapur district government authorities given stay for occupancy and sale on 19/08/2019. The stay has been withdrawn by government authorities on 13/10/2020. Due t…” Read the full reason“Obtained occupancy certificate(Partial) on 15/05/2019. Due to heavy rain in Kolhapur district government authorities given stay for occupancy and sale on 19/08/2019. The stay has been withdrawn by government authorities on 13/10/2020. Due to stay issued by department we not able complete the project so need the extension.”
  3. 27 June 2023

    Extended at the builder's request (MahaRERA application EXT53000012027)

    Reason the builder gave MahaRERA: “Revise sanction for Additional FSI from government authority and Covid - 19 Situation as well as fund shortage.”
  4. 28 August 2024

    Extended at the builder's request (MahaRERA application EXT53000016857)

    Reason the builder gave MahaRERA:
    “We have already completed the project. The completion file is pending with the concerned authority. Once the completion certificate has been received we will process the formation of Society and conveyance deed accordingly. Hence need exten…” Read the full reason“We have already completed the project. The completion file is pending with the concerned authority. Once the completion certificate has been received we will process the formation of Society and conveyance deed accordingly. Hence need extension of one year.”

Source: DATTATIRTH’s extension records on MahaRERA (P52100003610), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DATTATIRTH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100003610
Status
Lapsed (registration period ended)
Builder
GAJRAJ BUILDERS
Location
Kothrud, Kolhapur · 416106
Project type
Residential / Group Housing
Registered on
6 Aug 2017
Completion date at registration
July 2018
Latest completion date
August 2024
Delay so far
73 months
Homes
93
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of DATTATIRTH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%100%75%70%
B100%100%100%100%
C100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DATTATIRTH every month.

DATTATIRTH: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of DATTATIRTH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DATTATIRTH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DATTATIRTH

What is the possession date of DATTATIRTH?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DATTATIRTH in Kothrud, Kolhapur is 28 August 2024 — 73 months later than 31 July 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for DATTATIRTH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DATTATIRTH's builder has filed on MahaRERA, the official one, is 28 August 2024, already 73 months later than the 31 July 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DATTATIRTH extended?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH's builder applied to MahaRERA to extend the completion date 3 times: to 27 December 2021, giving the reason "Obtained occupancy certificate(Partial) on 15/05/2019. Due to heavy rain in Kolhapur district government authorities given stay for occupancy and sale on 19/08/2019. The stay has been withdrawn by government authorities on 13/10/2020. Due to stay issued by department we not able complete the project so need the extension."; to 27 June 2023, giving the reason "Revise sanction for Additional FSI from government authority and Covid - 19 Situation as well as fund shortage."; to 28 August 2024, giving the reason "We have already completed the project. The completion file is pending with the concerned authority. Once the completion certificate has been received we will process the formation of Society and conveyance deed accordingly. Hence need extension of one year.".

What is the RERA number of DATTATIRTH?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DATTATIRTH in Kothrud, Kolhapur is P52100003610.

Is DATTATIRTH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH is registered as P52100003610 and its status is "Lapsed (registration period ended)".

What is the construction status of DATTATIRTH?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does DATTATIRTH have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is DATTATIRTH safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH is registered on MahaRERA as P52100003610, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 73 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DATTATIRTH's possession date changes?

The latest dates are on DATTATIRTH's MahaRERA page (P52100003610). GharKundli's Kundli Watch sends a free WhatsApp update on DATTATIRTH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DATTATIRTH have?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH has 3 buildings filed: A with 5 floors; B with 6 floors; C with 6 floors.

How big is the land of DATTATIRTH?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH stands on 4,800 sq m of land (about 1.2 acres), with 3,941 sq m of sanctioned built-up area and 443 sq m of recreational open space.

Where can I read reviews of DATTATIRTH?

Google Maps has reviews of DATTATIRTH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DATTATIRTH?

DATTATIRTH by GAJRAJ BUILDERS is in Kothrud, Kolhapur (pincode 416106), near Narsobawadi, Maharashtra, and is registered on MahaRERA as P52100003610, per GharKundli's check of MahaRERA records.

How many homes are in DATTATIRTH?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH has 93 homes in 3 towers registered on MahaRERA.

When was DATTATIRTH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DATTATIRTH was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on DATTATIRTH?

No court cases are listed for DATTATIRTH on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of DATTATIRTH?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GAJRAJ BUILDERS.