Kapil Heights
by Arun Balasaheb Chougule HUF · Shahupuri, Kolhapur 416001Also near Kolhapur RS, Ispurli
What’s in the report? →Possession: Kapil Heights (MahaRERA P53000004217) is marked completed on MahaRERA. It has 14 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P53000004217. Status: Completed.
Source: MahaRERA website — records for P53000004217, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Kapil Heights?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Kapil Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000004217
- Status
- Completed
- Builder
- Arun Balasaheb Chougule HUF
- Location
- Shahupuri, Kolhapur · 416001
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- July 2019
- Homes
- 14
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Kapil Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KAPIL HEIGHTS | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kapil Heights every 1–2 months.
Kapil Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: KAPIL HEIGHTS (6 floors)
- Land: 216 sq m (about 0.1 acres) · sanctioned built-up 432 sq m
- Boundaries filed include: Corporation Road
- Land, as filed: 579 K
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kapil Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kapil Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kapil Heights
What is the possession date of Kapil Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kapil Heights in Shahupuri, Kolhapur is 31 July 2019.
Is the builder's possession date different from the MahaRERA date for Kapil Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kapil Heights's builder has filed on MahaRERA, the official one, is 31 July 2019, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Kapil Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kapil Heights in Shahupuri, Kolhapur is P53000004217.
Is Kapil Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights is registered as P53000004217 and its status is "Completed".
What is the current construction status of Kapil Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights's status on MahaRERA is "Completed". As filed by the builder, slab work on KAPIL HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Kapil Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Kapil Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights is registered on MahaRERA as P53000004217, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kapil Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Kapil Heights?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kapil Heights: gharkundli.com/tools/property-cost-calculator
Has Kapil Heights received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Kapil Heights completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights is marked completed on MahaRERA, and the completion date filed there is 31 July 2019. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Kapil Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Kapil Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kapil Heights's possession date changes?
The latest dates are on Kapil Heights's MahaRERA page (P53000004217). GharKundli's Kundli Watch sends a free WhatsApp update on Kapil Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kapil Heights have?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights has one building filed: KAPIL HEIGHTS with 6 floors.
How big is the land of Kapil Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights stands on 216 sq m of land (about 0.1 acres), with 432 sq m of sanctioned built-up area.
What are the reviews of Kapil Heights?
Google Maps has reviews of Kapil Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kapil Heights?
Kapil Heights by Arun Balasaheb Chougule HUF is in Shahupuri, Kolhapur, pincode 416001 (near Kolhapur RS, Ispurli), Maharashtra, and is registered on MahaRERA as P53000004217, per GharKundli's check of MahaRERA records. Its boundaries filed there include Corporation Road. Its land is filed as 579 K. GharKundli lists all 43 MahaRERA projects in Kolhapur (416001).
How many flats are in Kapil Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights has 14 homes in 1 tower registered on MahaRERA.
When was Kapil Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kapil Heights was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Does Kapil Heights have any legal issues or court cases?
No court cases are listed for Kapil Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Kapil Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Arun Balasaheb Chougule HUF.
Check it yourself on MahaRERA
- How to check the possession date of Kapil Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kolhapur (416001)
- Time Square
- Mark 1034
- Royal 09 Tourist Business Hub
- KP Empire
- Vardhaman Chintamani Wing C
- RDM Elite - Kissan
- Krishnae Residency
- Shri Mahalaxmi Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.