Possession: Gauri Lila is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53000008365. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Gauri Lila?
How the possession date of Gauri Lila has moved
30 December 2022
Completion date given when the project was registered
30 June 2024
Extended at the builder's request (MahaRERA application EXT53000013442)
Reason the builder gave MahaRERA:
“We applied for correction in June 2022 against which correction was granted to us. Now, the project is about to get completed and we have already made an application to the Kolhapur Municipal Corporation for the issue of the Completion Cert…” Read the full reason
“We applied for correction in June 2022 against which correction was granted to us. Now, the project is about to get completed and we have already made an application to the Kolhapur Municipal Corporation for the issue of the Completion Certificate. However, in order to complete the project entirely we require an extension of 1.5 years.”
Source: Gauri Lila’s extension records on MahaRERA (P53000008365), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gauri Lila
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000008365
- Status
- Completed
- Builder
- M/S Nashte Associates
- Location
- E Ward Kolhapur, Kolhapur · 416008
- Project type
- Others
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- June 2024
- Delay so far
- 18 months
- Homes
- 20
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
Construction progress of Gauri Lila, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Gauri Lila | 100% | 80% | 70% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gauri Lila every month.
Gauri Lila: buildings, flats and land, as filed on MahaRERA
- Buildings: Gauri Lila (6 floors)
- Land: 290 sq m (about 0.1 acres) · sanctioned built-up 1,157 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Gauri Lila →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gauri Lila: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Gauri Lila
What is the possession date of Gauri Lila?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Gauri Lila in E Ward Kolhapur, Kolhapur is 30 June 2024 — 18 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Gauri Lila?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gauri Lila's builder has filed on MahaRERA, the official one, is 30 June 2024, already 18 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gauri Lila extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila's builder applied to MahaRERA to extend the completion date once: to 30 June 2024, giving the reason "We applied for correction in June 2022 against which correction was granted to us. Now, the project is about to get completed and we have already made an application to the Kolhapur Municipal Corporation for the issue of the Completion Certificate. However, in order to complete the project entirely we require an extension of 1.5 years.".
What is the RERA number of Gauri Lila?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Gauri Lila in E Ward Kolhapur, Kolhapur is P53000008365.
Is Gauri Lila registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila is registered as P53000008365 and its status is "Completed".
What is the construction status of Gauri Lila?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila's status on MahaRERA is "Completed". As filed by the builder, slab work on Gauri Lila is 80% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Gauri Lila have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Gauri Lila safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila is registered on MahaRERA as P53000008365, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Gauri Lila's possession date changes?
The latest dates are on Gauri Lila's MahaRERA page (P53000008365). GharKundli's Kundli Watch sends a free WhatsApp update on Gauri Lila every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gauri Lila have?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila has one building filed: Gauri Lila with 6 floors.
How big is the land of Gauri Lila?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila stands on 290 sq m of land (about 0.1 acres), with 1,157 sq m of sanctioned built-up area.
Where can I read reviews of Gauri Lila?
Google Maps has reviews of Gauri Lila written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Gauri Lila?
Gauri Lila by M/S Nashte Associates is in E Ward Kolhapur, Kolhapur (pincode 416008), near Pratibhanagar, Maharashtra, and is registered on MahaRERA as P53000008365, per GharKundli's check of MahaRERA records.
How many homes are in Gauri Lila?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila has 20 homes in 1 tower registered on MahaRERA.
When was Gauri Lila registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Gauri Lila was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Gauri Lila?
3 court cases are listed for Gauri Lila on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Gauri Lila?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S Nashte Associates.
Check it yourself on MahaRERA
- How to check the possession date of Gauri Lila
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Karvir
- PUNYA SHLOK-TOWER 3
- KRISHNAE RESIDENCY
- YASHSHRI - GRAND LAKE VISTA
- TIME SQUARE
- MANGALAM IMPERIA
- Acharya Shree Vidyasagar
- VASANT VILLAS RESIDENCY
- SAPPHIRE SKY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.