Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shri Siddhivinayak Pride has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT53000009893)

    Reason the builder gave MahaRERA:
    “The development work of our Real Estate Project is going on. We have submitted the revised plan in respect of said project to the concerned Authority. Because of this we are unable to complete the said project in projected period i.e. on 30…” Read the full reason“The development work of our Real Estate Project is going on. We have submitted the revised plan in respect of said project to the concerned Authority. Because of this we are unable to complete the said project in projected period i.e. on 30/06/2021.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT53000013636)

    Reason the builder gave MahaRERA: “We have applied to Kolhapur Municipal Corporation for Revise Sanction Plan. Hence this project is not completed within timeline i.e.30/12/2022. So we have require for further extension for up to date 31/12/2024.”

Source: Shri Siddhivinayak Pride’s extension records on MahaRERA (P53000010585), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shri Siddhivinayak Pride

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53000010585
Status
Completed
Builder
Shree Siddhivinayak Builders and Developers
Location
Babujamal Road, Kolhapur · 416001
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2024
Delay so far
42 months
Homes
30
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Shri Siddhivinayak Pride, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shri Siddhivinayak Pride100%100%95%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shri Siddhivinayak Pride every month.

Shri Siddhivinayak Pride: buildings, flats and land, as filed on MahaRERA

  • Buildings: Shri Siddhivinayak Pride (8 floors)
  • Land: 749 sq m (about 0.2 acres) · sanctioned built-up 1,042 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shri Siddhivinayak Pride →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shri Siddhivinayak Pride: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shri Siddhivinayak Pride

What is the possession date of Shri Siddhivinayak Pride?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shri Siddhivinayak Pride in Babujamal Road, Kolhapur is 31 December 2024 — 42 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Shri Siddhivinayak Pride?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shri Siddhivinayak Pride's builder has filed on MahaRERA, the official one, is 31 December 2024, already 42 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shri Siddhivinayak Pride extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "The development work of our Real Estate Project is going on. We have submitted the revised plan in respect of said project to the concerned Authority. Because of this we are unable to complete the said project in projected period i.e. on 30/06/2021."; to 31 December 2024, giving the reason "We have applied to Kolhapur Municipal Corporation for Revise Sanction Plan. Hence this project is not completed within timeline i.e.30/12/2022. So we have require for further extension for up to date 31/12/2024.".

What is the RERA number of Shri Siddhivinayak Pride?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shri Siddhivinayak Pride in Babujamal Road, Kolhapur is P53000010585.

Is Shri Siddhivinayak Pride registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride is registered as P53000010585 and its status is "Completed".

What is the construction status of Shri Siddhivinayak Pride?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride's status on MahaRERA is "Completed". As filed by the builder, slab work on Shri Siddhivinayak Pride is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Shri Siddhivinayak Pride have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shri Siddhivinayak Pride safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride is registered on MahaRERA as P53000010585, its MahaRERA status is "Completed", its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shri Siddhivinayak Pride's possession date changes?

The latest dates are on Shri Siddhivinayak Pride's MahaRERA page (P53000010585). GharKundli's Kundli Watch sends a free WhatsApp update on Shri Siddhivinayak Pride every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shri Siddhivinayak Pride have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride has one building filed: Shri Siddhivinayak Pride with 8 floors.

How big is the land of Shri Siddhivinayak Pride?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride stands on 749 sq m of land (about 0.2 acres), with 1,042 sq m of sanctioned built-up area.

Where can I read reviews of Shri Siddhivinayak Pride?

Google Maps has reviews of Shri Siddhivinayak Pride written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shri Siddhivinayak Pride?

Shri Siddhivinayak Pride by Shree Siddhivinayak Builders and Developers is in Babujamal Road, Kolhapur (pincode 416001), Maharashtra, and is registered on MahaRERA as P53000010585, per GharKundli's check of MahaRERA records.

How many homes are in Shri Siddhivinayak Pride?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride has 30 homes in 1 tower registered on MahaRERA.

When was Shri Siddhivinayak Pride registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Siddhivinayak Pride was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Shri Siddhivinayak Pride?

No court cases are listed for Shri Siddhivinayak Pride on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Shri Siddhivinayak Pride?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Siddhivinayak Builders and Developers, which has 5 other projects registered on MahaRERA.

Other projects in Karvir

All 21 projects in Kolhapur (416001) →

Other projects by Shree Siddhivinayak Builders and Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.