Snap Bindu Pride
by SNAP REALTY · Bindu Chowk, 'C' Ward, Kolhapur 416002Registered on MahaRERA as “BINDU PRIDE”
What’s in the report? →Possession date of Snap Bindu Pride (MahaRERA P53000015112): 30 January 2022, moved from 31 January 2020 (24 months later), and it has already passed. It has 21 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P53000015112. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P53000015112, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (January 2022) has passed.
What do you want to know about Snap Bindu Pride?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Snap Bindu Pride has moved
31 January 2020
Completion date given when the project was registered
30 January 2021
Extended at the builder's request (MahaRERA application EXT53000005909)
Reason the builder gave MahaRERA:
“Our project is ready for occupancy. But we are waiting on the approval of road widening TDR from Kolhapur Municipal Corporation TP dept. for almost 9 months. Thereafter we will request for revised permission to utilize the road widening TDR…” Read the full reason
“Our project is ready for occupancy. But we are waiting on the approval of road widening TDR from Kolhapur Municipal Corporation TP dept. for almost 9 months. Thereafter we will request for revised permission to utilize the road widening TDR. Only after that we will be able to apply for Occupancy Certificate. We do not how long it will take to get all these approvals. Hence we are proposing and requesting to extend the project expiry date.”30 January 2022
Revised completion date on MahaRERA
Source: Snap Bindu Pride’s extension records on MahaRERA (P53000015112), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Snap Bindu Pride
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000015112
- Status
- Lapsed (registration period ended)
- Builder
- SNAP REALTY
- Location
- Bindu Chowk, 'C' Ward, Kolhapur · 416002
- Project type
- Commercial
- Registered on
- 31 Jan 2018
- Completion date at registration
- January 2020
- Latest completion date
- January 2022
- Delay so far
- 24 months
- Homes
- 21
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Snap Bindu Pride, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bindu Pride | 95% | 100% | 20% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Snap Bindu Pride every 1–2 months.
Snap Bindu Pride: buildings, flats and land, as filed on MahaRERA
- Buildings: Bindu Pride (9 floors)
- Land: 736 sq m (about 0.2 acres) · sanctioned built-up 1,509 sq m
- Boundaries filed include: Municipal Road, DRK Commerce College
- Land, as filed: CS. No 648, C - WARD
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Snap Bindu Pride →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Snap Bindu Pride: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Snap Bindu Pride
What is the possession date of Snap Bindu Pride?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Snap Bindu Pride in Bindu Chowk, 'C' Ward, Kolhapur is 30 January 2022 — 24 months later than 31 January 2020, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Snap Bindu Pride?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Snap Bindu Pride's builder has filed on MahaRERA, the official one, is 30 January 2022, already 24 months later than the 31 January 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Snap Bindu Pride extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride's builder applied to MahaRERA to extend the completion date once: to 30 January 2021, giving the reason "Our project is ready for occupancy. But we are waiting on the approval of road widening TDR from Kolhapur Municipal Corporation TP dept. for almost 9 months. Thereafter we will request for revised permission to utilize the road widening TDR. Only after that we will be able to apply for Occupancy Certificate. We do not how long it will take to get all these approvals. Hence we are proposing and requesting to extend the project expiry date.".
What is the RERA number of Snap Bindu Pride?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Snap Bindu Pride in Bindu Chowk, 'C' Ward, Kolhapur is P53000015112.
Is Snap Bindu Pride registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride is registered as P53000015112 and its status is "Lapsed (registration period ended)".
What is the current construction status of Snap Bindu Pride? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Bindu Pride is 100% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does Snap Bindu Pride have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Snap Bindu Pride safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride is registered on MahaRERA as P53000015112, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Snap Bindu Pride?
Snap Bindu Pride isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Snap Bindu Pride?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Snap Bindu Pride: gharkundli.com/tools/property-cost-calculator
Has Snap Bindu Pride received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 January 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Snap Bindu Pride?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 January 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Snap Bindu Pride uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Snap Bindu Pride was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Snap Bindu Pride's possession date changes?
The latest dates are on Snap Bindu Pride's MahaRERA page (P53000015112). GharKundli's Kundli Watch sends a free WhatsApp update on Snap Bindu Pride every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Snap Bindu Pride have?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride has one building filed: Bindu Pride with 9 floors.
How big is the land of Snap Bindu Pride?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride stands on 736 sq m of land (about 0.2 acres), with 1,509 sq m of sanctioned built-up area.
What are the reviews of Snap Bindu Pride?
Google Maps has reviews of Snap Bindu Pride written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Snap Bindu Pride?
Snap Bindu Pride by SNAP REALTY is in Bindu Chowk, 'C' Ward, Kolhapur, pincode 416002, Maharashtra, and is registered on MahaRERA as P53000015112, per GharKundli's check of MahaRERA records. Its boundaries filed there include Municipal Road, DRK Commerce College. Its land is filed as CS. No 648, C - WARD. GharKundli lists all 23 MahaRERA projects in Kolhapur (416002).
How many flats are in Snap Bindu Pride?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride has 21 homes in 1 tower registered on MahaRERA.
When was Snap Bindu Pride registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Snap Bindu Pride was registered on MahaRERA on 31 January 2018. GharKundli did not find a title report on the land on file there.
Does Snap Bindu Pride have any legal issues or court cases?
No court cases are listed for Snap Bindu Pride on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Snap Bindu Pride?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SNAP REALTY.
Check it yourself on MahaRERA
- How to check the possession date of Snap Bindu Pride
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Karvir
- Punya Shlok-tower 3
- Krishnae Residency
- Time Square
- Yashshri - Grand Lake Vista
- Mangalam Imperia
- Acharya Shree Vidyasagar
- Sapphire Sky
- Vasant Villas Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.