Rajani Vinayak

by Rajani Builders & Developers · E ward Near Vittal Mandir, Kolhapur

Possession date of Rajani Vinayak: 15 January 2024, moved from 30 December 2021 (25 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P53000015582. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (January 2024) has passed.

What do you want to know about Rajani Vinayak?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Rajani Vinayak has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 15 January 2024

    Extended at the builder's request (MahaRERA application EXT53000011596)

    Reason the builder gave MahaRERA: “We have obtained revised sanction from Kolhapur Municipal Corporation hence we have unable to complete said project in given timeline i.e 30/12/2021 so we have applied for extention”

Source: Rajani Vinayak’s extension records on MahaRERA (P53000015582), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rajani Vinayak

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53000015582
Status
Lapsed (registration period ended)
Builder
Rajani Builders & Developers
Location
E ward Near Vittal Mandir, Kolhapur · 416003
Project type
Others
Registered on
8 Mar 2018
Completion date at registration
December 2021
Latest completion date
January 2024
Delay so far
25 months
Homes
11
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Rajani Vinayak, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rajani Vinayak every month.

Rajani Vinayak: buildings, flats and land, as filed on MahaRERA

  • Buildings: A (6 floors)
  • Land: 372 sq m (about 0.1 acres) · sanctioned built-up 239 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Rajani Vinayak →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rajani Vinayak: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Rajani Vinayak

What is the possession date of Rajani Vinayak?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rajani Vinayak in E ward Near Vittal Mandir, Kolhapur is 15 January 2024 — 25 months later than 30 December 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Rajani Vinayak?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rajani Vinayak's builder has filed on MahaRERA, the official one, is 15 January 2024, already 25 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Rajani Vinayak extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak's builder applied to MahaRERA to extend the completion date once: to 15 January 2024, giving the reason "We have obtained revised sanction from Kolhapur Municipal Corporation hence we have unable to complete said project in given timeline i.e 30/12/2021 so we have applied for extention".

What is the RERA number of Rajani Vinayak?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rajani Vinayak in E ward Near Vittal Mandir, Kolhapur is P53000015582.

Is Rajani Vinayak registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak is registered as P53000015582 and its status is "Lapsed (registration period ended)".

What is the construction status of Rajani Vinayak?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Rajani Vinayak have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Rajani Vinayak safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak is registered on MahaRERA as P53000015582, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Rajani Vinayak's possession date changes?

The latest dates are on Rajani Vinayak's MahaRERA page (P53000015582). GharKundli's Kundli Watch sends a free WhatsApp update on Rajani Vinayak every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rajani Vinayak have?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak has one building filed: A with 6 floors.

How big is the land of Rajani Vinayak?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak stands on 372 sq m of land (about 0.1 acres), with 239 sq m of sanctioned built-up area.

Where can I read reviews of Rajani Vinayak?

Google Maps has reviews of Rajani Vinayak written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Rajani Vinayak?

Rajani Vinayak by Rajani Builders & Developers is in E ward Near Vittal Mandir, Kolhapur (pincode 416003), Maharashtra, and is registered on MahaRERA as P53000015582, per GharKundli's check of MahaRERA records.

How many homes are in Rajani Vinayak?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak has 11 homes in 1 tower registered on MahaRERA.

When was Rajani Vinayak registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajani Vinayak was registered on MahaRERA on 8 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Rajani Vinayak?

No court cases are listed for Rajani Vinayak on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Rajani Vinayak?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Rajani Builders & Developers.

Other projects in Karvir

All 70 projects in Kolhapur (416003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.