ROHINI APPARTMENT

by SUJATA SAMIR MODI · Mahad, Raigarh

Possession date of ROHINI APPARTMENT: 31 March 2019, moved from 31 March 2018 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed.

Registered on MahaRERA under P52000011263. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2019) has passed.

GharKundli’s full report on ROHINI APPARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000011263
Status
Lapsed (registration period ended)
Builder
SUJATA SAMIR MODI
Location
Mahad, Raigarh · 402301
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
March 2018
Latest completion date
March 2019
Delay so far
12 months
Homes
13
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of ROHINI APPARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ROHINI APPARTMENT100%100%95%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ROHINI APPARTMENT every month.

ROHINI APPARTMENT: buildings, flats and land, as filed on MahaRERA

Kundli Watch

ROHINI APPARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ROHINI APPARTMENT

What is the possession date of ROHINI APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ROHINI APPARTMENT in Mahad, Raigarh is 31 March 2019 — 12 months later than 31 March 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for ROHINI APPARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ROHINI APPARTMENT's builder has filed on MahaRERA, the official one, is 31 March 2019, already 12 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of ROHINI APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ROHINI APPARTMENT in Mahad, Raigarh is P52000011263.

Is ROHINI APPARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ROHINI APPARTMENT is registered as P52000011263 and its status is "Lapsed (registration period ended)".

What is the construction status of ROHINI APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), ROHINI APPARTMENT's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ROHINI APPARTMENT is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does ROHINI APPARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is ROHINI APPARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ROHINI APPARTMENT is registered on MahaRERA as P52000011263, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ROHINI APPARTMENT's possession date changes?

The latest dates are on ROHINI APPARTMENT's MahaRERA page (P52000011263). GharKundli's Kundli Watch sends a free WhatsApp update on ROHINI APPARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ROHINI APPARTMENT have?

According to GharKundli's check of MahaRERA records (updated November 2026), ROHINI APPARTMENT has one building filed: ROHINI APPARTMENT with 6 floors.

How big is the land of ROHINI APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), ROHINI APPARTMENT stands on 232 sq m of land (about 0.1 acres), with 462 sq m of sanctioned built-up area.

Where is ROHINI APPARTMENT?

ROHINI APPARTMENT by SUJATA SAMIR MODI is in Mahad, Raigarh (pincode 402301), Maharashtra, and is registered on MahaRERA as P52000011263, per GharKundli's check of MahaRERA records.

How many homes are in ROHINI APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), ROHINI APPARTMENT has 13 homes in 1 tower registered on MahaRERA.

When was ROHINI APPARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ROHINI APPARTMENT was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ROHINI APPARTMENT?

1 court case is listed for ROHINI APPARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ROHINI APPARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SUJATA SAMIR MODI, which has 1 other project registered on MahaRERA.