GOODWILL RESIDENCY

by KIFAYAT ABDUL KADIR MATWANKAR · Mahad, Raigarh

Possession date of GOODWILL RESIDENCY: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000024696, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GOODWILL RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GOODWILL RESIDENCY has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52000013648)

    Reason the builder gave MahaRERA: “due to covid construction work was delayed”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52000027339)

    Reason the builder gave MahaRERA: “The Construction is yet to be Completed”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA31012619666)

    Reason the builder gave MahaRERA: “the said project is in the mahad city and it is near by river there is flood every year here and because of flood and low labour avaliability the extension is required to complete entire project”
  5. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GOODWILL RESIDENCY’s extension records on MahaRERA (P52000024696), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GOODWILL RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000024696
Status
Registered and active
Builder
KIFAYAT ABDUL KADIR MATWANKAR
Location
Mahad, Raigarh · 402301
Project type
Others
Registered on
28 Feb 2020
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
14
Sold or booked
46%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GOODWILL RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GOODWILL RESIDENCY100%100%80%50%

Commencement certificate (CC), as filed on MahaRERA

  • GOODWILL RESIDENCY: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOODWILL RESIDENCY every month.

GOODWILL RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: GOODWILL RESIDENCY (5 floors, 19 units)
  • Land: 321 sq m (about 0.1 acres) · sanctioned built-up 643 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GOODWILL RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GOODWILL RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GOODWILL RESIDENCY

What is the possession date of GOODWILL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GOODWILL RESIDENCY in Mahad, Raigarh is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GOODWILL RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GOODWILL RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GOODWILL RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2024, giving the reason "due to covid construction work was delayed"; to 31 December 2025, giving the reason "The Construction is yet to be Completed"; to 31 December 2027, giving the reason "the said project is in the mahad city and it is near by river there is flood every year here and because of flood and low labour avaliability the extension is required to complete entire project". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of GOODWILL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GOODWILL RESIDENCY in Mahad, Raigarh is P52000024696.

Is GOODWILL RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY is registered as P52000024696 and its status is "Registered and active".

What is the construction status of GOODWILL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GOODWILL RESIDENCY is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does GOODWILL RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GOODWILL RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY is registered on MahaRERA as P52000024696, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GOODWILL RESIDENCY's possession date changes?

The latest dates are on GOODWILL RESIDENCY's MahaRERA page (P52000024696). GharKundli's Kundli Watch sends a free WhatsApp update on GOODWILL RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GOODWILL RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY has one building filed: GOODWILL RESIDENCY with 5 floors and 19 units.

How big is the land of GOODWILL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY stands on 321 sq m of land (about 0.1 acres), with 643 sq m of sanctioned built-up area.

Where can I read reviews of GOODWILL RESIDENCY?

Google Maps has reviews of GOODWILL RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GOODWILL RESIDENCY?

GOODWILL RESIDENCY by KIFAYAT ABDUL KADIR MATWANKAR is in Mahad, Raigarh (pincode 402301), Maharashtra, and is registered on MahaRERA as P52000024696, per GharKundli's check of MahaRERA records.

How many homes are in GOODWILL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY has 14 homes in 1 tower registered on MahaRERA, and 46% of them are sold or booked.

When was GOODWILL RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOODWILL RESIDENCY was registered on MahaRERA on 28 February 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on GOODWILL RESIDENCY?

No court cases are listed for GOODWILL RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GOODWILL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KIFAYAT ABDUL KADIR MATWANKAR.

All projects with possession due in 2028 in Raigad →

Other projects in pincode 402301

All 94 projects in Mahad (402301) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.