Registered on MahaRERA under P52000022025. Status: Completed. Its completion date has moved from June 2022 to June 2024, 24 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on SHAMBHO HOMES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000022025
- Status
- Completed
- Builder
- VISHWANATH HARISCHANDRA EKAWADE
- Location
- Neral, Raigarh · 410101
- Project type
- Others
- Registered on
- 25 Aug 2019
- Completion date at registration
- June 2022
- Latest completion date
- June 2024
- Delay so far
- 24 months
- Homes
- 52
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
SHAMBHO HOMES: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHAMBHO HOMES
Is SHAMBHO HOMES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHAMBHO HOMES is registered as P52000022025 and its status is "Completed".
Where is SHAMBHO HOMES?
SHAMBHO HOMES by VISHWANATH HARISCHANDRA EKAWADE is in Neral, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000022025, per GharKundli's check of MahaRERA records.
When is possession of SHAMBHO HOMES due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHAMBHO HOMES in Neral, Raigarh is 30 June 2024 — 24 months later than 30 June 2022, the date given at registration.
Does SHAMBHO HOMES have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in SHAMBHO HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), SHAMBHO HOMES has 52 homes in 1 tower registered on MahaRERA.
When was SHAMBHO HOMES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHAMBHO HOMES was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SHAMBHO HOMES?
No court cases are listed for SHAMBHO HOMES on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHAMBHO HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISHWANATH HARISCHANDRA EKAWADE.