How the possession date of SAI SINDHU has moved

  1. 31 July 2019

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52100012700)

    Reason the builder gave MahaRERA: “COVID AND NON AVAILABILITY OF RESOURCES.”

Source: SAI SINDHU’s extension records on MahaRERA (P52100001923), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI SINDHU

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100001923
Status
Completed
Builder
SHREE VIGHNAHAR PROMOTERS AND BUILDERS PVT LTD
Location
Sahyadri Farm Society, Pune · 410502
Project type
Residential / Group Housing
Registered on
29 Jul 2017
Completion date at registration
July 2019
Latest completion date
December 2023
Delay so far
53 months
Homes
34
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SAI SINDHU, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI SINDHU100%100%60%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI SINDHU every month.

SAI SINDHU: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI SINDHU (6 floors)
  • Land: 1,275 sq m (about 0.3 acres) · sanctioned built-up 1,530 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI SINDHU →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI SINDHU: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI SINDHU

What is the possession date of SAI SINDHU?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI SINDHU in Sahyadri Farm Society, Pune is 31 December 2023 — 53 months later than 31 July 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI SINDHU?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI SINDHU's builder has filed on MahaRERA, the official one, is 31 December 2023, already 53 months later than the 31 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI SINDHU extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU's builder applied to MahaRERA to extend the completion date once: to 31 December 2023, giving the reason "COVID AND NON AVAILABILITY OF RESOURCES.".

What is the RERA number of SAI SINDHU?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI SINDHU in Sahyadri Farm Society, Pune is P52100001923.

Is SAI SINDHU registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU is registered as P52100001923 and its status is "Completed".

What is the construction status of SAI SINDHU?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU's status on MahaRERA is "Completed". As filed by the builder, slab work on SAI SINDHU is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does SAI SINDHU have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAI SINDHU safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU is registered on MahaRERA as P52100001923, its MahaRERA status is "Completed", its completion date has moved 53 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI SINDHU's possession date changes?

The latest dates are on SAI SINDHU's MahaRERA page (P52100001923). GharKundli's Kundli Watch sends a free WhatsApp update on SAI SINDHU every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI SINDHU have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU has one building filed: SAI SINDHU with 6 floors.

How big is the land of SAI SINDHU?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU stands on 1,275 sq m of land (about 0.3 acres), with 1,530 sq m of sanctioned built-up area.

Where can I read reviews of SAI SINDHU?

Google Maps has reviews of SAI SINDHU written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI SINDHU?

SAI SINDHU by SHREE VIGHNAHAR PROMOTERS AND BUILDERS PVT LTD is in Sahyadri Farm Society, Pune (pincode 410502), Maharashtra, and is registered on MahaRERA as P52100001923, per GharKundli's check of MahaRERA records.

How many homes are in SAI SINDHU?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU has 34 homes in 1 tower registered on MahaRERA.

When was SAI SINDHU registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SINDHU was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI SINDHU?

No court cases are listed for SAI SINDHU on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI SINDHU?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE VIGHNAHAR PROMOTERS AND BUILDERS PVT LTD, which has 1 other project registered on MahaRERA.