OM PARADISE A WING

by S K BUILDCON · kiwale, PuneAlso near Dehu Road Cantt

Possession: OM PARADISE A WING is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100008127. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about OM PARADISE A WING?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of OM PARADISE A WING has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 May 2022

    Extended at the builder's request (MahaRERA application EXT52100011461)

    Reason the builder gave MahaRERA:
    “Project development work has been completed and we have already applied to completent authority for completion certificate vide receipt no 103321220000293 date 07/04/2021 but the same is awaited it has delayed due guideline ferquently issus…” Read the full reason“Project development work has been completed and we have already applied to completent authority for completion certificate vide receipt no 103321220000293 date 07/04/2021 but the same is awaited it has delayed due guideline ferquently issused by govt due to covid 19 regarding restriction for offices thus we have completed the project br fore period extended by rera authority vide registration certificate date 09-09-2021”

Source: OM PARADISE A WING’s extension records on MahaRERA (P52100008127), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on OM PARADISE A WING

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100008127
Status
Completed
Builder
S K BUILDCON
Location
kiwale, Pune · 412101
Project type
Residential / Group Housing
Registered on
18 Aug 2017
Completion date at registration
December 2021
Latest completion date
May 2022
Delay so far
5 months
Homes
42
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of OM PARADISE A WING, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
OM PARADISE A WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on OM PARADISE A WING every month.

OM PARADISE A WING: buildings, flats and land, as filed on MahaRERA

  • Buildings: OM PARADISE A WING (7 floors)
  • Land: 857 sq m (about 0.2 acres) · sanctioned built-up 1,204 sq m · recreational space 387 sq m
  • Boundaries filed include: MUMBAI BANGLORE HIGHWAY

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of OM PARADISE A WING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

OM PARADISE A WING: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about OM PARADISE A WING

What is the possession date of OM PARADISE A WING?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OM PARADISE A WING in kiwale, Pune is 31 May 2022 — 5 months later than 30 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for OM PARADISE A WING?

Builders and listing sites often quote an earlier "target" date for handover. The completion date OM PARADISE A WING's builder has filed on MahaRERA, the official one, is 31 May 2022, already 5 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of OM PARADISE A WING extended?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING's builder applied to MahaRERA to extend the completion date once: to 31 May 2022, giving the reason "Project development work has been completed and we have already applied to completent authority for completion certificate vide receipt no 103321220000293 date 07/04/2021 but the same is awaited it has delayed due guideline ferquently issused by govt due to covid 19 regarding restriction for offices thus we have completed the project br fore period extended by rera authority vide registration certificate date 09-09-2021".

What is the RERA number of OM PARADISE A WING?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OM PARADISE A WING in kiwale, Pune is P52100008127.

Is OM PARADISE A WING registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING is registered as P52100008127 and its status is "Completed".

What is the construction status of OM PARADISE A WING?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING's status on MahaRERA is "Completed". As filed by the builder, slab work on OM PARADISE A WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does OM PARADISE A WING have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is OM PARADISE A WING safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING is registered on MahaRERA as P52100008127, its MahaRERA status is "Completed", its completion date has moved 5 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if OM PARADISE A WING's possession date changes?

The latest dates are on OM PARADISE A WING's MahaRERA page (P52100008127). GharKundli's Kundli Watch sends a free WhatsApp update on OM PARADISE A WING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does OM PARADISE A WING have?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING has one building filed: OM PARADISE A WING with 7 floors.

How big is the land of OM PARADISE A WING?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING stands on 857 sq m of land (about 0.2 acres), with 1,204 sq m of sanctioned built-up area and 387 sq m of recreational open space.

Where can I read reviews of OM PARADISE A WING?

Google Maps has reviews of OM PARADISE A WING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is OM PARADISE A WING?

OM PARADISE A WING by S K BUILDCON is in kiwale, Pune (pincode 412101), near Dehu Road Cantt, Maharashtra, and is registered on MahaRERA as P52100008127, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUMBAI BANGLORE HIGHWAY.

How many homes are in OM PARADISE A WING?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING has 42 homes in 1 tower registered on MahaRERA.

When was OM PARADISE A WING registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PARADISE A WING was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on OM PARADISE A WING?

No court cases are listed for OM PARADISE A WING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of OM PARADISE A WING?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is S K BUILDCON, which has 7 other projects registered on MahaRERA.