SITANGAN PLAZA

by SHREE CHINTAMANI DEVELOPERS · Kasarwadi, PuneAlso near Pimple Gurav

Possession: SITANGAN PLAZA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100015950. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SITANGAN PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SITANGAN PLAZA has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 31 October 2022

    Extended at the builder's request (MahaRERA application EXT52100012147)

    Reason the builder gave MahaRERA: “REVISED PLAN OF 1ST FLOOR WAS SANCTIONED BY PCMC ON 09.02.2022 HENCE WE ARE APPLYING FOR EXTENTION OF COMPLETION OF THE PROJECT.”

Source: SITANGAN PLAZA’s extension records on MahaRERA (P52100015950), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SITANGAN PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100015950
Status
Completed
Builder
SHREE CHINTAMANI DEVELOPERS
Location
Kasarwadi, Pune · 411034
Project type
Others
Registered on
9 Apr 2018
Completion date at registration
June 2022
Latest completion date
October 2022
Delay so far
4 months
Homes
32
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of SITANGAN PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SITANGAN PLAZA0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SITANGAN PLAZA every month.

SITANGAN PLAZA: buildings, flats and land, as filed on MahaRERA

  • Buildings: SITANGAN PLAZA (8 floors)
  • Land: 770 sq m (about 0.2 acres) · sanctioned built-up 995 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SITANGAN PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SITANGAN PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SITANGAN PLAZA

What is the possession date of SITANGAN PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SITANGAN PLAZA in Kasarwadi, Pune is 31 October 2022 — 4 months later than 30 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SITANGAN PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SITANGAN PLAZA's builder has filed on MahaRERA, the official one, is 31 October 2022, already 4 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SITANGAN PLAZA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA's builder applied to MahaRERA to extend the completion date once: to 31 October 2022, giving the reason "REVISED PLAN OF 1ST FLOOR WAS SANCTIONED BY PCMC ON 09.02.2022 HENCE WE ARE APPLYING FOR EXTENTION OF COMPLETION OF THE PROJECT.".

What is the RERA number of SITANGAN PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SITANGAN PLAZA in Kasarwadi, Pune is P52100015950.

Is SITANGAN PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA is registered as P52100015950 and its status is "Completed".

What is the construction status of SITANGAN PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA's status on MahaRERA is "Completed". As filed by the builder, slab work on SITANGAN PLAZA is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SITANGAN PLAZA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SITANGAN PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA is registered on MahaRERA as P52100015950, its MahaRERA status is "Completed", its completion date has moved 4 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SITANGAN PLAZA's possession date changes?

The latest dates are on SITANGAN PLAZA's MahaRERA page (P52100015950). GharKundli's Kundli Watch sends a free WhatsApp update on SITANGAN PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SITANGAN PLAZA have?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA has one building filed: SITANGAN PLAZA with 8 floors.

How big is the land of SITANGAN PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA stands on 770 sq m of land (about 0.2 acres), with 995 sq m of sanctioned built-up area.

Where can I read reviews of SITANGAN PLAZA?

Google Maps has reviews of SITANGAN PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SITANGAN PLAZA?

SITANGAN PLAZA by SHREE CHINTAMANI DEVELOPERS is in Kasarwadi, Pune (pincode 411034), near Pimple Gurav, Maharashtra, and is registered on MahaRERA as P52100015950, per GharKundli's check of MahaRERA records.

How many homes are in SITANGAN PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA has 32 homes in 1 tower registered on MahaRERA.

When was SITANGAN PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SITANGAN PLAZA was registered on MahaRERA on 9 April 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SITANGAN PLAZA?

No court cases are listed for SITANGAN PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SITANGAN PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE CHINTAMANI DEVELOPERS, which has 4 other projects registered on MahaRERA.