Skip to content
GharKundli

LAXMI KUNJ

by M K CONSTRUCTION · Kirtane Baug, Pune

Possession: LAXMI KUNJ is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100027524. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about LAXMI KUNJ?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LAXMI KUNJ has moved

  1. 30 September 2022

    Completion date given when the project was registered

  2. 30 April 2024

    Extended at the builder's request (MahaRERA application EXT52100011932)

    Reason the builder gave MahaRERA:
    “Due to Covid pandemic we were unable to resume with our construction work and due to this reason we need to extend our project completion date to 30th April 2024. As we have not sold a single apartment so no need of any consent required. Ki…” Read the full reason“Due to Covid pandemic we were unable to resume with our construction work and due to this reason we need to extend our project completion date to 30th April 2024. As we have not sold a single apartment so no need of any consent required. Kindly issue us the fresh extended RERA registration Certificate. It is hereby prayed that our request may kindly be accepted.”

Source: LAXMI KUNJ’s extension records on MahaRERA (P52100027524), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LAXMI KUNJ

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100027524
Status
Completed
Builder
M K CONSTRUCTION
Location
Kirtane Baug, Pune · 411036
Project type
Residential / Group Housing
Registered on
14 Dec 2020
Completion date at registration
September 2022
Latest completion date
April 2024
Delay so far
19 months
Homes
28
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of LAXMI KUNJ, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LAXMI KUNJ100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAXMI KUNJ every month.

LAXMI KUNJ: buildings, flats and land, as filed on MahaRERA

  • Buildings: LAXMI KUNJ (8 floors)
  • Land: 1,207 sq m (about 0.3 acres) · sanctioned built-up 970 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of LAXMI KUNJ →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LAXMI KUNJ: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LAXMI KUNJ

What is the possession date of LAXMI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for LAXMI KUNJ in Kirtane Baug, Pune is 30 April 2024 — 19 months later than 30 September 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for LAXMI KUNJ?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LAXMI KUNJ's builder has filed on MahaRERA, the official one, is 30 April 2024, already 19 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of LAXMI KUNJ extended?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ's builder applied to MahaRERA to extend the completion date once: to 30 April 2024, giving the reason "Due to Covid pandemic we were unable to resume with our construction work and due to this reason we need to extend our project completion date to 30th April 2024. As we have not sold a single apartment so no need of any consent required. Kindly issue us the fresh extended RERA registration Certificate. It is hereby prayed that our request may kindly be accepted.".

What is the RERA number of LAXMI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of LAXMI KUNJ in Kirtane Baug, Pune is P52100027524.

Is LAXMI KUNJ registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ is registered as P52100027524 and its status is "Completed".

What is the construction status of LAXMI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ's status on MahaRERA is "Completed". As filed by the builder, slab work on LAXMI KUNJ is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does LAXMI KUNJ have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is LAXMI KUNJ safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ is registered on MahaRERA as P52100027524, its MahaRERA status is "Completed", its completion date has moved 19 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LAXMI KUNJ's possession date changes?

The latest dates are on LAXMI KUNJ's MahaRERA page (P52100027524). GharKundli's Kundli Watch sends a free WhatsApp update on LAXMI KUNJ every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LAXMI KUNJ have?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ has one building filed: LAXMI KUNJ with 8 floors.

How big is the land of LAXMI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ stands on 1,207 sq m of land (about 0.3 acres), with 970 sq m of sanctioned built-up area.

Where can I read reviews of LAXMI KUNJ?

Google Maps has reviews of LAXMI KUNJ written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LAXMI KUNJ?

LAXMI KUNJ by M K CONSTRUCTION is in Kirtane Baug, Pune (pincode 411036), Maharashtra, and is registered on MahaRERA as P52100027524, per GharKundli's check of MahaRERA records.

How many homes are in LAXMI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ has 28 homes in 1 tower registered on MahaRERA.

When was LAXMI KUNJ registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI KUNJ was registered on MahaRERA on 14 December 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on LAXMI KUNJ?

No court cases are listed for LAXMI KUNJ on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of LAXMI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M K CONSTRUCTION.

Other projects in Pune City

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.