GOKULDHAAM
by SETU DEVELOPERS · Shirur, PuneAlso near Talegaon Dhamdhere
Possession date of GOKULDHAAM: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100033484, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about GOKULDHAAM?
How the possession date of GOKULDHAAM has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GOKULDHAAM’s extension records on MahaRERA (P52100033484), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GOKULDHAAM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100033484
- Status
- Registered and active
- Builder
- SETU DEVELOPERS
- Location
- Shirur, Pune · 412208
- Project type
- Residential / Group Housing
- Registered on
- 22 Feb 2022
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 96
- Sold or booked
- 39%
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GOKULDHAAM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A1 | 100% | 19% | 0% | 0% |
| WING A2 | 100% | 19% | 0% | 0% |
| WING A3 | 0% | 0% | 0% | 0% |
| WING A4 | 0% | 0% | 0% | 0% |
| WING A5 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A1: covers 4 floors
- WING A2: covers 4 floors
- WING A3: covers 4 floors
- WING A4: covers 4 floors
- WING A5: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOKULDHAAM every month.
GOKULDHAAM: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A1 (7 floors, 24 units) · WING A2 (7 floors, 24 units) · WING A3 (7 floors, 24 units) · WING A4 (7 floors, 24 units) · WING A5 (7 floors)
- Car parking: 20 open
- Land: 3,650 sq m (about 0.9 acres) · sanctioned built-up 3,932 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GOKULDHAAM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GOKULDHAAM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GOKULDHAAM
What is the possession date of GOKULDHAAM?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GOKULDHAAM in Shirur, Pune is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GOKULDHAAM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GOKULDHAAM's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of GOKULDHAAM?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GOKULDHAAM in Shirur, Pune is P52100033484.
Is GOKULDHAAM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GOKULDHAAM is registered as P52100033484 and its status is "Registered and active".
What is the construction status of GOKULDHAAM?
According to GharKundli's check of MahaRERA records (updated November 2026), GOKULDHAAM's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 19% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does GOKULDHAAM have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is GOKULDHAAM safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), GOKULDHAAM is registered on MahaRERA as P52100033484, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GOKULDHAAM's possession date changes?
The latest dates are on GOKULDHAAM's MahaRERA page (P52100033484). GharKundli's Kundli Watch sends a free WhatsApp update on GOKULDHAAM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GOKULDHAAM have?
According to GharKundli's check of MahaRERA records (updated November 2026), GOKULDHAAM has 5 buildings filed: WING A1 with 7 floors and 24 units; WING A2 with 7 floors and 24 units; WING A3 with 7 floors and 24 units; WING A4 with 7 floors and 24 units; WING A5 with 7 floors.
How much parking does GOKULDHAAM have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 20 open car parking spaces for GOKULDHAAM.
How big is the land of GOKULDHAAM?
According to GharKundli's check of MahaRERA records (updated November 2026), GOKULDHAAM stands on 3,650 sq m of land (about 0.9 acres), with 3,932 sq m of sanctioned built-up area.
Where can I read reviews of GOKULDHAAM?
Google Maps has reviews of GOKULDHAAM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GOKULDHAAM?
GOKULDHAAM by SETU DEVELOPERS is in Shirur, Pune (pincode 412208), near Talegaon Dhamdhere, Maharashtra, and is registered on MahaRERA as P52100033484, per GharKundli's check of MahaRERA records.
How many homes are in GOKULDHAAM?
According to GharKundli's check of MahaRERA records (updated November 2026), GOKULDHAAM has 96 homes in 5 towers registered on MahaRERA, and 39% of them are sold or booked.
When was GOKULDHAAM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GOKULDHAAM was registered on MahaRERA on 22 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on GOKULDHAAM?
No court cases are listed for GOKULDHAAM on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of GOKULDHAAM?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SETU DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of GOKULDHAAM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 412208
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.