Skip to content
GharKundli

ZAR EMPIRE

by ZAR BUILDERS & DEVELOPERS · Waliv Vasai East, Palghar

Possession: ZAR EMPIRE is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000009027. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ZAR EMPIRE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ZAR EMPIRE has moved

  1. 31 January 2021

    Completion date given when the project was registered

  2. 31 January 2022

    Extended at the builder's request (MahaRERA application EXT99000009180)

    Reason the builder gave MahaRERA: “Project work is more than 90% complete. Remaining work will be complete very and application for OC will be done.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000012927)

    Reason the builder gave MahaRERA: “OC not received”

Source: ZAR EMPIRE’s extension records on MahaRERA (P99000009027), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ZAR EMPIRE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000009027
Status
Completed
Builder
ZAR BUILDERS & DEVELOPERS
Location
Waliv Vasai East, Palghar · 401208
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
January 2021
Latest completion date
December 2025
Delay so far
59 months
Homes
373
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of ZAR EMPIRE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ZAR EMPIRE100%60%60%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ZAR EMPIRE every month.

ZAR EMPIRE: buildings, flats and land, as filed on MahaRERA

  • Buildings: ZAR EMPIRE (19 floors)
  • Land: 5,105 sq m (about 1.3 acres) · sanctioned built-up 6,868 sq m · recreational space 1,216 sq m

The builder’s record and reviews

ZAR Builders & Developers has 3 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of ZAR EMPIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ZAR EMPIRE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ZAR EMPIRE

What is the possession date of ZAR EMPIRE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ZAR EMPIRE in Waliv Vasai East, Palghar is 31 December 2025 — 59 months later than 31 January 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for ZAR EMPIRE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ZAR EMPIRE's builder has filed on MahaRERA, the official one, is 31 December 2025, already 59 months later than the 31 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ZAR EMPIRE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE's builder applied to MahaRERA to extend the completion date 2 times: to 31 January 2022, giving the reason "Project work is more than 90% complete. Remaining work will be complete very and application for OC will be done."; to 31 December 2025, giving the reason "OC not received".

What is the RERA number of ZAR EMPIRE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ZAR EMPIRE in Waliv Vasai East, Palghar is P99000009027.

Is ZAR EMPIRE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE is registered as P99000009027 and its status is "Completed".

What is the construction status of ZAR EMPIRE?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE's status on MahaRERA is "Completed". As filed by the builder, slab work on ZAR EMPIRE is 60% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does ZAR EMPIRE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is ZAR EMPIRE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE is registered on MahaRERA as P99000009027, its MahaRERA status is "Completed", its completion date has moved 59 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ZAR EMPIRE's possession date changes?

The latest dates are on ZAR EMPIRE's MahaRERA page (P99000009027). GharKundli's Kundli Watch sends a free WhatsApp update on ZAR EMPIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ZAR EMPIRE have?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE has one building filed: ZAR EMPIRE with 19 floors.

How big is the land of ZAR EMPIRE?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE stands on 5,105 sq m of land (about 1.3 acres), with 6,868 sq m of sanctioned built-up area and 1,216 sq m of recreational open space.

What is the track record of ZAR EMPIRE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR Builders & Developers has 3 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ZAR EMPIRE?

Google Maps has reviews of ZAR EMPIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ZAR EMPIRE?

ZAR EMPIRE by ZAR BUILDERS & DEVELOPERS is in Waliv Vasai East, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000009027, per GharKundli's check of MahaRERA records.

How many homes are in ZAR EMPIRE?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE has 373 homes in 1 tower registered on MahaRERA.

When was ZAR EMPIRE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ZAR EMPIRE was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ZAR EMPIRE?

No court cases are listed for ZAR EMPIRE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ZAR EMPIRE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ZAR BUILDERS & DEVELOPERS, which has 2 other projects registered on MahaRERA.

Other projects in Vasai

Other projects by ZAR BUILDERS & DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.