NIDHI REALTY PHASE I

by LALIT NAGINDAS DOSHI · Malad West, Palghar

Possession: NIDHI REALTY PHASE I is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000002258. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about NIDHI REALTY PHASE I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NIDHI REALTY PHASE I has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT99000003782)

    Reason the builder gave MahaRERA: “DUE TO SHORTAGE OF LAND AND DELAY IN SUBMISSION THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST TO PLEASE GRANT US EXTENSION TILL 31/12/2020. ALL THE REQUIREMENTS HAS BEEN FULFILLED.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT99000011306)

    Reason the builder gave MahaRERA: “covide has lead in crunch in financial position of every one and non availability of labor power on time lead us to extend the project to certain extent”

Source: NIDHI REALTY PHASE I’s extension records on MahaRERA (P99000002258), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NIDHI REALTY PHASE I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000002258
Status
Completed
Builder
LALIT NAGINDAS DOSHI
Location
Malad West, Palghar · 401208
Project type
Mixed
Registered on
31 Jul 2017
Completion date at registration
December 2018
Latest completion date
December 2024
Delay so far
72 months
Homes
31
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of NIDHI REALTY PHASE I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SONAL INDUSTRIES100%97%97%97%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIDHI REALTY PHASE I every month.

NIDHI REALTY PHASE I: buildings, flats and land, as filed on MahaRERA

  • Buildings: SONAL INDUSTRIES (3 floors)
  • Land: 6,799 sq m (about 1.7 acres) · sanctioned built-up 3,568 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NIDHI REALTY PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NIDHI REALTY PHASE I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NIDHI REALTY PHASE I

What is the possession date of NIDHI REALTY PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIDHI REALTY PHASE I in Malad West, Palghar is 31 December 2024 — 72 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NIDHI REALTY PHASE I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NIDHI REALTY PHASE I's builder has filed on MahaRERA, the official one, is 31 December 2024, already 72 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NIDHI REALTY PHASE I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2020, giving the reason "DUE TO SHORTAGE OF LAND AND DELAY IN SUBMISSION THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST TO PLEASE GRANT US EXTENSION TILL 31/12/2020. ALL THE REQUIREMENTS HAS BEEN FULFILLED."; to 31 December 2024, giving the reason "covide has lead in crunch in financial position of every one and non availability of labor power on time lead us to extend the project to certain extent".

What is the RERA number of NIDHI REALTY PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIDHI REALTY PHASE I in Malad West, Palghar is P99000002258.

Is NIDHI REALTY PHASE I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I is registered as P99000002258 and its status is "Completed".

What is the construction status of NIDHI REALTY PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I's status on MahaRERA is "Completed". As filed by the builder, slab work on SONAL INDUSTRIES is 97% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.

Does NIDHI REALTY PHASE I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NIDHI REALTY PHASE I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I is registered on MahaRERA as P99000002258, its MahaRERA status is "Completed", its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NIDHI REALTY PHASE I's possession date changes?

The latest dates are on NIDHI REALTY PHASE I's MahaRERA page (P99000002258). GharKundli's Kundli Watch sends a free WhatsApp update on NIDHI REALTY PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NIDHI REALTY PHASE I have?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I has one building filed: SONAL INDUSTRIES with 3 floors.

How big is the land of NIDHI REALTY PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I stands on 6,799 sq m of land (about 1.7 acres), with 3,568 sq m of sanctioned built-up area.

Where can I read reviews of NIDHI REALTY PHASE I?

Google Maps has reviews of NIDHI REALTY PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NIDHI REALTY PHASE I?

NIDHI REALTY PHASE I by LALIT NAGINDAS DOSHI is in Malad West, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000002258, per GharKundli's check of MahaRERA records.

How many homes are in NIDHI REALTY PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I has 31 homes in 1 tower registered on MahaRERA.

When was NIDHI REALTY PHASE I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIDHI REALTY PHASE I was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NIDHI REALTY PHASE I?

No court cases are listed for NIDHI REALTY PHASE I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NIDHI REALTY PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LALIT NAGINDAS DOSHI, which has 1 other project registered on MahaRERA.