Possession date of URBAN FOREST B WING: 31 December 2023, moved from 31 December 2018 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100007315. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about URBAN FOREST B WING?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of URBAN FOREST B WING has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT52100001678)

    Reason the builder gave MahaRERA: “IN FINAL STAGE OF TILING WORK”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52100012434)

    Reason the builder gave MahaRERA: “LIFT FITTING WORK IN PROGRESS WILL GET IT COMPLETED AS SOON AS POSSIBLE”

Source: URBAN FOREST B WING’s extension records on MahaRERA (P52100007315), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on URBAN FOREST B WING

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100007315
Status
Lapsed (registration period ended)
Builder
EKDANTA NEST LLP
Location
Dapodi, Pune · 410401
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2023
Delay so far
60 months
Homes
56
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of URBAN FOREST B WING, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
URBAN FOREST B WING100%100%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on URBAN FOREST B WING every month.

URBAN FOREST B WING: buildings, flats and land, as filed on MahaRERA

  • Buildings: URBAN FOREST B WING (9 floors)
  • Land: 7,300 sq m (about 1.8 acres) · sanctioned built-up 3,289 sq m · recreational space 668 sq m

The builder’s record and reviews

Ganeshconstruction (a group of 3 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 8 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of URBAN FOREST B WING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

URBAN FOREST B WING: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about URBAN FOREST B WING

What is the possession date of URBAN FOREST B WING?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for URBAN FOREST B WING in Dapodi, Pune is 31 December 2023 — 60 months later than 31 December 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for URBAN FOREST B WING?

Builders and listing sites often quote an earlier "target" date for handover. The completion date URBAN FOREST B WING's builder has filed on MahaRERA, the official one, is 31 December 2023, already 60 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of URBAN FOREST B WING extended?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2019, giving the reason "IN FINAL STAGE OF TILING WORK"; to 31 December 2023, giving the reason "LIFT FITTING WORK IN PROGRESS WILL GET IT COMPLETED AS SOON AS POSSIBLE".

What is the RERA number of URBAN FOREST B WING?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of URBAN FOREST B WING in Dapodi, Pune is P52100007315.

Is URBAN FOREST B WING registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING is registered as P52100007315 and its status is "Lapsed (registration period ended)".

What is the construction status of URBAN FOREST B WING?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on URBAN FOREST B WING is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does URBAN FOREST B WING have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is URBAN FOREST B WING safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING is registered on MahaRERA as P52100007315, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if URBAN FOREST B WING's possession date changes?

The latest dates are on URBAN FOREST B WING's MahaRERA page (P52100007315). GharKundli's Kundli Watch sends a free WhatsApp update on URBAN FOREST B WING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does URBAN FOREST B WING have?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING has one building filed: URBAN FOREST B WING with 9 floors.

How big is the land of URBAN FOREST B WING?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING stands on 7,300 sq m of land (about 1.8 acres), with 3,289 sq m of sanctioned built-up area and 668 sq m of recreational open space.

What is the track record of URBAN FOREST B WING's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganeshconstruction (a group of 3 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 8 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of URBAN FOREST B WING?

Google Maps has reviews of URBAN FOREST B WING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is URBAN FOREST B WING?

URBAN FOREST B WING by EKDANTA NEST LLP is in Dapodi, Pune (pincode 410401), Maharashtra, and is registered on MahaRERA as P52100007315, per GharKundli's check of MahaRERA records.

How many homes are in URBAN FOREST B WING?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING has 56 homes in 1 tower registered on MahaRERA.

When was URBAN FOREST B WING registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), URBAN FOREST B WING was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on URBAN FOREST B WING?

No court cases are listed for URBAN FOREST B WING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of URBAN FOREST B WING?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is EKDANTA NEST LLP, which has 6 other projects registered on MahaRERA.

Other projects in Dapodi

Other projects by EKDANTA NEST LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.