Aashritha Phase II
by YOGVINDA PROMOTERS AND DEVELOPERS PVT LTD · Patil Nagar Chikhali, Pune
Possession: Aashritha Phase II is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100018886. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Aashritha Phase II?
How the possession date of Aashritha Phase II has moved
25 June 2022
Completion date given when the project was registered
25 December 2022
Extended at the builder's request (MahaRERA application EXT52100012419)
Reason the builder gave MahaRERA:
“Dear Sir/Madam, All civil work of Aashritha phase II is completed. Aashritha Phase II completion is in process with PCMC authority ,and some part of Aashritha phase II completion is received, for reaming part of Aashritha phase II.Kindly gr…” Read the full reason
“Dear Sir/Madam, All civil work of Aashritha phase II is completed. Aashritha Phase II completion is in process with PCMC authority ,and some part of Aashritha phase II completion is received, for reaming part of Aashritha phase II.Kindly grant us extension period of next 6 months 25.12.2022, so we can complete all necessary process for completion paper work of AASHRITHA PHASE II. Thanks & Regards YOGVINDA PROMOTERS & DEVELOPERS PVT. LTD.”
Source: Aashritha Phase II’s extension records on MahaRERA (P52100018886), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aashritha Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100018886
- Status
- Completed
- Builder
- YOGVINDA PROMOTERS AND DEVELOPERS PVT LTD
- Location
- Patil Nagar Chikhali, Pune · 411062
- Project type
- Residential / Group Housing
- Registered on
- 10 Dec 2018
- Completion date at registration
- June 2022
- Latest completion date
- December 2022
- Delay so far
- 6 months
- Homes
- 89
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Aashritha Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 100% | 100% | 100% | 100% |
| B WING | 100% | 100% | 100% | 100% |
| C WING | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aashritha Phase II every month.
Aashritha Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: A WING (10 floors) · B WING (8 floors) · C WING (10 floors)
- Land: 3,500 sq m (about 0.9 acres) · sanctioned built-up 5,215 sq m · recreational space 350 sq m
The builder’s record and reviews
Yogvinda Promoters & Developers (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 34 months); 4 still being built, 1 past the promised date (typically 2 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Aashritha Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aashritha Phase II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Aashritha Phase II
What is the possession date of Aashritha Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aashritha Phase II in Patil Nagar Chikhali, Pune is 25 December 2022 — 6 months later than 25 June 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Aashritha Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aashritha Phase II's builder has filed on MahaRERA, the official one, is 25 December 2022, already 6 months later than the 25 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aashritha Phase II extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II's builder applied to MahaRERA to extend the completion date once: to 25 December 2022, giving the reason "Dear Sir/Madam, All civil work of Aashritha phase II is completed. Aashritha Phase II completion is in process with PCMC authority ,and some part of Aashritha phase II completion is received, for reaming part of Aashritha phase II.Kindly grant us extension period of next 6 months 25.12.2022, so we can complete all necessary process for completion paper work of AASHRITHA PHASE II. Thanks & Regards YOGVINDA PROMOTERS & DEVELOPERS PVT. LTD.".
What is the RERA number of Aashritha Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aashritha Phase II in Patil Nagar Chikhali, Pune is P52100018886.
Is Aashritha Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II is registered as P52100018886 and its status is "Completed".
What is the construction status of Aashritha Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Aashritha Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Aashritha Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II is registered on MahaRERA as P52100018886, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Aashritha Phase II's possession date changes?
The latest dates are on Aashritha Phase II's MahaRERA page (P52100018886). GharKundli's Kundli Watch sends a free WhatsApp update on Aashritha Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aashritha Phase II have?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II has 3 buildings filed: A WING with 10 floors; B WING with 8 floors; C WING with 10 floors.
How big is the land of Aashritha Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II stands on 3,500 sq m of land (about 0.9 acres), with 5,215 sq m of sanctioned built-up area and 350 sq m of recreational open space.
What is the track record of Aashritha Phase II's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Yogvinda Promoters & Developers (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 34 months); 4 still being built, 1 past the promised date (typically 2 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Aashritha Phase II?
Google Maps has reviews of Aashritha Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Aashritha Phase II?
Aashritha Phase II by YOGVINDA PROMOTERS AND DEVELOPERS PVT LTD is in Patil Nagar Chikhali, Pune (pincode 411062), Maharashtra, and is registered on MahaRERA as P52100018886, per GharKundli's check of MahaRERA records.
How many homes are in Aashritha Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II has 89 homes in 3 towers registered on MahaRERA.
When was Aashritha Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aashritha Phase II was registered on MahaRERA on 10 December 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Aashritha Phase II?
No court cases are listed for Aashritha Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Aashritha Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is YOGVINDA PROMOTERS AND DEVELOPERS PVT LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Aashritha Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
Other projects by YOGVINDA PROMOTERS AND DEVELOPERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.