by Tushar Mohanrao Khatavkar · E ward, KolhapurAlso near Rajarampuri, Takala, Pratibhanagar

Possession: TULIP ELEMENT is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P53000026601. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about TULIP ELEMENT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TULIP ELEMENT has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT53000014007)

    Reason the builder gave MahaRERA: “The development work of my Real Estate Project is going on. we are unable to complete the said project in projected period i.e. on 30/12/2022.hence we have applied for extension.”

Source: TULIP ELEMENT’s extension records on MahaRERA (P53000026601), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TULIP ELEMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53000026601
Status
Completed
Builder
Tushar Mohanrao Khatavkar
Location
E ward, Kolhapur · 416008
Project type
Others
Registered on
7 Oct 2020
Completion date at registration
December 2022
Latest completion date
December 2024
Delay so far
24 months
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of TULIP ELEMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tulip Element100%20%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULIP ELEMENT every month.

TULIP ELEMENT: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of TULIP ELEMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TULIP ELEMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TULIP ELEMENT

What is the possession date of TULIP ELEMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TULIP ELEMENT in E ward, Kolhapur is 31 December 2024 — 24 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for TULIP ELEMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TULIP ELEMENT's builder has filed on MahaRERA, the official one, is 31 December 2024, already 24 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TULIP ELEMENT extended?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT's builder applied to MahaRERA to extend the completion date once: to 31 December 2024, giving the reason "The development work of my Real Estate Project is going on. we are unable to complete the said project in projected period i.e. on 30/12/2022.hence we have applied for extension.".

What is the RERA number of TULIP ELEMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TULIP ELEMENT in E ward, Kolhapur is P53000026601.

Is TULIP ELEMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT is registered as P53000026601 and its status is "Completed".

What is the construction status of TULIP ELEMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT's status on MahaRERA is "Completed". As filed by the builder, slab work on Tulip Element is 20% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does TULIP ELEMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is TULIP ELEMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT is registered on MahaRERA as P53000026601, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TULIP ELEMENT's possession date changes?

The latest dates are on TULIP ELEMENT's MahaRERA page (P53000026601). GharKundli's Kundli Watch sends a free WhatsApp update on TULIP ELEMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TULIP ELEMENT have?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT has one building filed: Tulip Element with 9 floors.

How big is the land of TULIP ELEMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT stands on 145 sq m of land (about 0.0 acres), with 277 sq m of sanctioned built-up area.

Where can I read reviews of TULIP ELEMENT?

Google Maps has reviews of TULIP ELEMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TULIP ELEMENT?

TULIP ELEMENT by Tushar Mohanrao Khatavkar is in E ward, Kolhapur (pincode 416008), near Rajarampuri, Takala, Pratibhanagar, Maharashtra, and is registered on MahaRERA as P53000026601, per GharKundli's check of MahaRERA records.

How many homes are in TULIP ELEMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT has 12 homes in 1 tower registered on MahaRERA.

When was TULIP ELEMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP ELEMENT was registered on MahaRERA on 7 October 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on TULIP ELEMENT?

No court cases are listed for TULIP ELEMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of TULIP ELEMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Tushar Mohanrao Khatavkar, which has 3 other projects registered on MahaRERA.

Other projects in Karvir

All 37 projects in Pratibhanagar (416008) →

Other projects by Tushar Mohanrao Khatavkar

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.