Skip to content
GharKundli

The Hub

by AIM KAPADE CREATORS · Shaniwar Peth S.O (Kolhapur), Kolhapur 416002

What’s in the report? →

Possession: The Hub (MahaRERA P53000024315) is marked completed on MahaRERA. It has 16 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P53000024315. Status: Completed.

Source: MahaRERA website — records for P53000024315, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The Hub?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on The Hub

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53000024315
Status
Completed
Builder
AIM KAPADE CREATORS
Location
Shaniwar Peth S.O (Kolhapur), Kolhapur · 416002
Project type
Others
Registered on
3 Feb 2020
Completion date at registration
December 2023
Latest completion date
December 2023
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of The Hub, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
THE HUB100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Hub every 1–2 months.

The Hub: buildings, flats and land, as filed on MahaRERA

  • Buildings: THE HUB (6 floors)
  • Land: 446 sq m (about 0.1 acres) · sanctioned built-up 885 sq m
  • Land, as filed: C.S.NO750/1 AND 750/2
  • Map: Get directions

The builder’s record and reviews

AIM Kapade Creators has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA.

Read Google reviews of The Hub →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Hub: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Hub

What is the possession date of The Hub?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Hub in Shaniwar Peth S.O (Kolhapur), Kolhapur is 1 December 2023.

Is the builder's possession date different from the MahaRERA date for The Hub?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Hub's builder has filed on MahaRERA, the official one, is 1 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of The Hub?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Hub in Shaniwar Peth S.O (Kolhapur), Kolhapur is P53000024315.

Is The Hub registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub is registered as P53000024315 and its status is "Completed".

What is the current construction status of The Hub? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub's status on MahaRERA is "Completed". As filed by the builder, slab work on THE HUB is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does The Hub have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is The Hub safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub is registered on MahaRERA as P53000024315, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Hub?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in The Hub?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in The Hub: gharkundli.com/tools/property-cost-calculator

Has The Hub received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was The Hub completed?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub is marked completed on MahaRERA, and the completion date filed there is 1 December 2023. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has The Hub uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for The Hub was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Hub's possession date changes?

The latest dates are on The Hub's MahaRERA page (P53000024315). GharKundli's Kundli Watch sends a free WhatsApp update on The Hub every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Hub have?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub has one building filed: THE HUB with 6 floors.

How big is the land of The Hub?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub stands on 446 sq m of land (about 0.1 acres), with 885 sq m of sanctioned built-up area.

What is the track record of The Hub's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), AIM Kapade Creators has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of The Hub?

Google Maps has reviews of The Hub written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Hub?

The Hub by AIM KAPADE CREATORS is in Shaniwar Peth S.O (Kolhapur), Kolhapur, pincode 416002, Maharashtra, and is registered on MahaRERA as P53000024315, per GharKundli's check of MahaRERA records. Its land is filed as C.S.NO750/1 AND 750/2. GharKundli lists all 23 MahaRERA projects in Kolhapur (416002).

How many flats are in The Hub?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub has 16 homes in 1 tower registered on MahaRERA.

When was The Hub registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Hub was registered on MahaRERA on 3 February 2020. GharKundli did not find a title report on the land on file there.

Does The Hub have any legal issues or court cases?

No court cases are listed for The Hub on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of The Hub?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AIM KAPADE CREATORS, which has 1 other project registered on MahaRERA.

Other projects in Kolhapur (416002)

All 23 projects in Kolhapur (416002) →

Other projects by AIM KAPADE CREATORS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.