Possession date of Shri Narayan Bhavan (MahaRERA P53000025183): 30 December 2025, and it has already passed. It has 12 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P53000025183. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P53000025183, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Shri Narayan Bhavan?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Shri Narayan Bhavan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53000025183
Status
Lapsed (registration period ended)
Builder
Hanmant Dhondappa Gurav
Location
Nera Mahadev Mandir, Kolhapur · 416115
Project type
Residential / Group Housing
Registered on
23 Mar 2020
Completion date at registration
December 2025
Latest completion date
December 2025
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shri Narayan Bhavan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shri Narayan Bhavan100%50%20%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shri Narayan Bhavan every 1–2 months.

Shri Narayan Bhavan: buildings, flats and land, as filed on MahaRERA

  • Buildings: Shri Narayan Bhavan (5 floors)
  • Land: 213 sq m (about 0.1 acres) · sanctioned built-up 441 sq m
  • Land, as filed: 2611 B and 2629
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shri Narayan Bhavan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shri Narayan Bhavan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shri Narayan Bhavan

What is the possession date of Shri Narayan Bhavan?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shri Narayan Bhavan in Nera Mahadev Mandir, Kolhapur is 30 December 2025. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shri Narayan Bhavan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shri Narayan Bhavan's builder has filed on MahaRERA, the official one, is 30 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shri Narayan Bhavan?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shri Narayan Bhavan in Nera Mahadev Mandir, Kolhapur is P53000025183.

Is Shri Narayan Bhavan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan is registered as P53000025183 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shri Narayan Bhavan? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shri Narayan Bhavan is 50% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does Shri Narayan Bhavan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shri Narayan Bhavan safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan is registered on MahaRERA as P53000025183, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shri Narayan Bhavan?

Shri Narayan Bhavan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shri Narayan Bhavan?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shri Narayan Bhavan: gharkundli.com/tools/property-cost-calculator

Has Shri Narayan Bhavan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shri Narayan Bhavan?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shri Narayan Bhavan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shri Narayan Bhavan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shri Narayan Bhavan's possession date changes?

The latest dates are on Shri Narayan Bhavan's MahaRERA page (P53000025183). GharKundli's Kundli Watch sends a free WhatsApp update on Shri Narayan Bhavan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shri Narayan Bhavan have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan has one building filed: Shri Narayan Bhavan with 5 floors.

How big is the land of Shri Narayan Bhavan?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan stands on 213 sq m of land (about 0.1 acres), with 441 sq m of sanctioned built-up area.

What are the reviews of Shri Narayan Bhavan?

Google Maps has reviews of Shri Narayan Bhavan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shri Narayan Bhavan?

Shri Narayan Bhavan by Hanmant Dhondappa Gurav is in Nera Mahadev Mandir, Kolhapur, pincode 416115, Maharashtra, and is registered on MahaRERA as P53000025183, per GharKundli's check of MahaRERA records. Its land is filed as 2611 B and 2629. GharKundli lists all 59 MahaRERA projects in Ichalkaranji (416115).

How many flats are in Shri Narayan Bhavan?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan has 12 homes in 1 tower registered on MahaRERA.

When was Shri Narayan Bhavan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Narayan Bhavan was registered on MahaRERA on 23 March 2020. GharKundli did not find a title report on the land on file there.

Does Shri Narayan Bhavan have any legal issues or court cases?

No court cases are listed for Shri Narayan Bhavan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Shri Narayan Bhavan?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Hanmant Dhondappa Gurav.

Other projects in Hatkanangle

All 59 projects in Ichalkaranji (416115) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.